10412 W CROCKETT ST 91352

Certificate Information: 10412 W CROCKETT ST 91352

Application / Permit
23016-20000-22686
Plan Check / Job No.
B23VN09189
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE ATTACHED TO EXISTING RECREATION ROOM TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - ALL WORK PER WFPP AND SUPPLEMENTARY ENGINEERED DETAIL
Permit Issued
Issued on 8/11/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/18/2023 JESSE ARELLANO
Corrections Issued 7/19/2023 JESSE ARELLANO
Building Plans Picked Up 7/27/2023 APPLICANT
Issued 8/11/2023 APPLICANT
CofO in Progress 7/16/2025 GAREN HAYRAPETYAN
Permit Finaled 7/16/2025 RUBEN SALAS
CofO Issued 7/16/2025 RUBEN SALAS
Permit Finaled 7/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/27/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/27/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/28/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Mario A; Lic. No.: C89006 1942 SPANISH BROOM DR      PALMDALE, CA 93550

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/8/2024 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 7/26/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/5/2024 Approved DAVID ANDERSON
PLUMBING-Rough 8/5/2024 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 9/12/2024 Approved DAVID ANDERSON
Green Building Rough 9/12/2024 Approved DAVID ANDERSON
MERV13>=Rough 9/12/2024 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 9/12/2024 Approved DAVID ANDERSON
Insulation 9/19/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 9/19/2024 Partial Approval DAVID ANDERSON
Shower Pan 9/19/2024 Approved DAVID ANDERSON
Drywall Nailing 10/2/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/2/2024 Approved DAVID ANDERSON
Sewer 2/21/2025 Approved DAVID ANDERSON
Underground Mechanical 2/21/2025 Approved DAVID ANDERSON
Final 5/2/2025 Corrections Issued DAVID ANDERSON
Green Building Final 5/2/2025 Not Ready for Inspection DAVID ANDERSON
MERV13>=Final 5/2/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 5/2/2025 Not Ready for Inspection DAVID ANDERSON
Final 5/23/2025 Not Ready for Inspection DAVID ANDERSON
Green Building Final 5/23/2025 Approved DAVID ANDERSON
Smoke Detectors 5/23/2025 Approved DAVID ANDERSON
Final 7/15/2025 OK to Issue CofO GAREN HAYRAPETYAN