5065 N CANOGA AVE 91364
Certificate Information: 5065 N CANOGA AVE 91364
- Application / Permit
- 23016-20000-22572
- Plan Check / Job No.
- B23VN09141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A NEW 18'-0" x 20'-0" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 10/14/2023
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 7/29/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/13/2023 | LUISANGEL VALENZUELA |
| Issued | 10/14/2023 | APPLICANT |
| CofO in Progress | 10/11/2024 | JOHN HAYES |
| Permit Finaled | 11/15/2024 | JOHN JANSON |
| CofO Issued | 11/15/2024 | JOHN JANSON |
| Permit Finaled | 11/15/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2023 | CARLOS AGUILERA |
| Historic monument | Cleared | 8/1/2023 | STEVEN WECHSLER |
| Sewer availability | Cleared | 8/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/1/2023 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 10/10/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 10/13/2023 | SARKIS HARABEDIAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 6/10/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/12/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 6/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/17/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 6/17/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/9/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/9/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 7/15/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/15/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/15/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/18/2024 | Conditional Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/18/2024 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 7/23/2024 | Approved | JOHN HAYES |
| Sewer | 7/26/2024 | Corrections Issued | JOHN HAYES |
| Drywall Nailing | 7/30/2024 | Approved | JOHN HAYES |
| Sewer | 7/30/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 7/30/2024 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 8/6/2024 | Approved | JOHN HAYES |
| Shower Pan | 8/6/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 8/6/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 9/27/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/27/2024 | Corrections Issued | JOHN HAYES |
| HVAC-Final | 9/27/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 9/27/2024 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/27/2024 | Approved | JOHN HAYES |
| Final | 10/7/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Not Ready | JOHN HAYES |
| Final | 10/10/2024 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | JOHN HAYES |