9300 N BALCOM AVE 91325
Certificate Information: 9300 N BALCOM AVE 91325
- Application / Permit
- 23016-20000-22568
- Plan Check / Job No.
- B23VN07525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE INTO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22 **ePlan**
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- Issued on 2/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/10/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/18/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/1/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/7/2023 | NILOOFAR MEHRAIN |
| Issued | 2/9/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2023 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 10/17/2023 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/20/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/16/2024 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 7/16/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/5/2024 | Approved | JAVIER RAMOS JR |
| Sewer | 10/3/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 10/3/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/23/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/30/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 8/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 9/16/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Shower Pan | 9/22/2025 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 1/9/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 6/1/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Insulation | 6/1/2026 | Not Ready for Inspection | KEVIN BERBERYAN |