7104 N OAKDALE AVE 91306

Certificate Information: 7104 N OAKDALE AVE 91306

Application / Permit
23016-20000-22446
Plan Check / Job No.
B23VN09074
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/10/2023 APPLICANT
Assigned to Plan Check Engineer 7/14/2023 KAMYAR EMAMI
Corrections Issued 7/14/2023 KAMYAR EMAMI
Building Plans Picked Up 7/17/2023 APPLICANT
Plan Check Approved 7/18/2023 ALEC MOUSAKHANIAN
Issued 7/18/2023 APPLICANT
CofO in Progress 9/18/2024 ARUTYUN MADATYAN
Permit Finaled 9/25/2024 JOHN JANSON
CofO Issued 9/25/2024 JOHN JANSON
Permit Finaled 9/25/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/15/2023 CARLOS AGUILERA
Sewer availability Cleared 7/15/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/17/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 5/8/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 5/17/2024 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 6/14/2024 Corrections Issued ARUTYUN MADATYAN
Interior/Exterior Lathing 7/8/2024 Partial Approval KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 7/8/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 7/10/2024 Partial Approval ARUTYUN MADATYAN
Insulation 7/17/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 7/19/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Approved ALEXANDER HANDY
Drywall Nailing 7/25/2024 Approved ARUTYUN MADATYAN
Sewer 8/12/2024 Approved ARUTYUN MADATYAN
Underground Mechanical 8/16/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 8/30/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 8/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
Final 8/30/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 8/30/2024 Approved ARUTYUN MADATYAN
Green Building Rough 8/30/2024 Approved ARUTYUN MADATYAN
HVAC-Final 8/30/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 8/30/2024 No Access for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 8/30/2024 Approved ARUTYUN MADATYAN
Final 9/10/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 9/18/2024 Approved ARUTYUN MADATYAN
Final 9/18/2024 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 9/18/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 9/18/2024 Approved ARUTYUN MADATYAN
Service/Power Release 9/18/2024 Approved ARUTYUN MADATYAN