7434 N GENESTA AVE 91406

Certificate Information: 7434 N GENESTA AVE 91406

Application / Permit
23016-20000-22310
Plan Check / Job No.
B23VN09022
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE & WORKSHOP TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2023 APPLICANT
Assigned to Plan Check Engineer 7/12/2023 SERGIO MUNIZ
Corrections Issued 7/13/2023 SERGIO MUNIZ
Building Plans Picked Up 7/14/2023 APPLICANT
Plan Check Approved 11/14/2023 ANGELICA MARTINEZ
Issued 11/16/2023 APPLICANT
CofO in Progress 5/31/2024 RAUL OLAGI
Permit Finaled 6/25/2024 RUBEN SALAS
CofO Issued 6/25/2024 RUBEN SALAS
Permit Finaled 6/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/1/2023 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/1/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 8/2/2023 MARKOS PEREZ-BRAN
Construction within easement Cleared 11/4/2023 RIDWAN HARDY

Contact Information

Contractor Nextdoor Construction And Remodeling Inc; Lic. No.: 1061320-B 18653 VENTURA BLVD #393      TARZANA, CA 91356
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/2/2024 Conditional Approval JUAN VALENZUELA
Underground Mechanical 2/6/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/8/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/13/2024 Corrections Issued RAUL OLAGI
Sewer 2/13/2024 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 2/15/2024 Approved RAUL OLAGI
Sewer 2/28/2024 Approved RAUL OLAGI
Underground Mechanical 2/28/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 3/14/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 3/14/2024 Approved RAUL OLAGI
HVAC-Rough 3/14/2024 Approved RAUL OLAGI
PLUMBING-Rough 3/14/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/21/2024 Approved RAUL OLAGI
Green Building Rough 3/21/2024 Approved RAUL OLAGI
Insulation 3/21/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 3/21/2024 Approved RAUL OLAGI
Drywall Nailing 3/27/2024 Approved RAUL OLAGI
Final 5/10/2024 Corrections Issued RAUL OLAGI
Green Building Final 5/10/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/10/2024 Approved RAUL OLAGI
Final 5/30/2024 OK to Issue CofO RAUL OLAGI