16105-16107 W HARVEST ST 91344
Certificate Information: 16105-16107 W HARVEST ST 91344
- Application / Permit
- 23016-20000-21862
- Plan Check / Job No.
- B23VN08842
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'10" X 21' ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK TO BE DONE PER ENGINEER.
- Permit Issued
- Issued on 8/31/2023
- Issuing Office
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2023 | WEIJIAN HUANG |
| Corrections Issued | 7/11/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 8/15/2023 | MADISON ODELL |
| Plan Check Approved | 8/30/2023 | DAVID CASTILLO |
| Issued | 8/31/2023 | APPLICANT |
| CofO in Progress | 5/2/2024 | JAVIER RAMOS JR |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
| CofO Issued | 5/31/2024 | RUBEN SALAS |
| Permit Finaled | 5/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/18/2023 | TAL SHEMEN |
| Address approval | Cleared | 7/24/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 8/16/2023 | WEIJIAN HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samvelyan,, Taron; Lic. No.: C93740 | 1800 N VERDUGO RD APT 204 GLENDALE, CA 91208 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 11/21/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 12/15/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 1/4/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/16/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 1/16/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JAVIER RAMOS JR |
| Gas Test | 1/29/2024 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 1/29/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 1/29/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 2/2/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/2/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 2/2/2024 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 2/2/2024 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/18/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 4/18/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 4/18/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/18/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/30/2024 | Approved | JAVIER RAMOS JR |
| Final | 4/30/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 4/30/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/30/2024 | Approved | JAVIER RAMOS JR |