9942 N SHOUP AVE 91311
Certificate Information: 9942 N SHOUP AVE 91311
- Application / Permit
- 23016-20000-21719
- Plan Check / Job No.
- B23VN08795
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Conversion of (E) detached Garage and Storage room to an ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) using WFPP
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | EDWIN ESPIN |
| Corrections Issued | 7/8/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/26/2023 | AMY GUEVARRA |
| Plan Check Approved | 8/3/2023 | AMY GUEVARRA |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 5/15/2024 | JEFFREY HARTLINE |
| Permit Finaled | 5/22/2024 | JOHN JANSON |
| CofO Issued | 5/22/2024 | JOHN JANSON |
| Permit Finaled | 5/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/18/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 7/21/2023 | SERGIO VALENZUELA |
| GPI Written Notices | Cleared | 7/26/2023 | AMY GUEVARRA |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: NA33143 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2023 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/11/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 9/12/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/14/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/14/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 9/14/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/4/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/4/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/4/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/4/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/10/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/10/2023 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/12/2023 | Approved | JEFFREY HARTLINE |
| Insulation | 10/12/2023 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 10/17/2023 | Approved | JEFFREY HARTLINE |
| Shower Pan | 10/17/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/25/2023 | Approved | JEFFREY HARTLINE |
| Final | 2/26/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 2/26/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | JEFFREY HARTLINE |
| Smoke Detectors | 2/26/2024 | Approved | JEFFREY HARTLINE |
| Final | 3/5/2024 | Corrections Issued | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Final | 5/14/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 5/14/2024 | Approved | JEFFREY HARTLINE |