4042 N CARTWRIGHT AVE 91604
Certificate Information: 4042 N CARTWRIGHT AVE 91604
- Application / Permit
- 23016-20000-21718
- Plan Check / Job No.
- B23VN08792
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 8/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2023 | JOHNPAUL ISIP |
| Corrections Issued | 7/12/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 1/11/2024 | JOHNPAUL ISIP |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 8/2/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
| CofO Issued | 8/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/31/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2023 | CARLOS AGUILERA |
| ZI | Cleared | 9/5/2023 | RUBEN VASQUEZ |
| Construction within easement | Cleared | 1/8/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2024 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 2/13/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 2/13/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 2/15/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 2/26/2024 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Rough | 2/26/2024 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 2/28/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/4/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 3/4/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 3/4/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/11/2024 | Partial Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/11/2024 | Approved | JOHN COLEMAN |
| HVAC-Rough | 3/11/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 3/11/2024 | Approved | JOHN COLEMAN |
| Insulation | 3/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 3/18/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 3/18/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/21/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/21/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/27/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 6/27/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 6/27/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 6/27/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 7/10/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/10/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 7/10/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 7/10/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/16/2024 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 8/2/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 8/2/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 8/2/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 8/2/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 8/2/2024 | Approved | CHRISTOPHER ROJAS |