4042 N CARTWRIGHT AVE 91604

Certificate Information: 4042 N CARTWRIGHT AVE 91604

Application / Permit
23016-20000-21718
Plan Check / Job No.
B23VN08792
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 8/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2023 APPLICANT
Assigned to Plan Check Engineer 7/11/2023 JOHNPAUL ISIP
Corrections Issued 7/12/2023 JOHNPAUL ISIP
Plan Check Approved 1/11/2024 JOHNPAUL ISIP
Issued 1/18/2024 APPLICANT
CofO in Progress 8/2/2024 CHRISTOPHER ROJAS
Permit Finaled 8/12/2024 DANIEL ORRANTE
CofO Issued 8/12/2024 DANIEL ORRANTE
Permit Finaled 8/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/31/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/31/2023 CARLOS AGUILERA
Sewer availability Cleared 8/31/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/5/2023 CARLOS AGUILERA
ZI Cleared 9/5/2023 RUBEN VASQUEZ
Construction within easement Cleared 1/8/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/13/2024 Approved KIRK SANDERS
Footing/Foundation/Slab 2/13/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 2/13/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 2/15/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/26/2024 Corrections Issued KIRK SANDERS
Green Building Rough 2/26/2024 Not Ready for Inspection KIRK SANDERS
MERV13>=Rough 2/26/2024 Approved KIRK SANDERS
Deputy Wood Construction 2/28/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 3/4/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval KIRK SANDERS
Green Building Rough 3/4/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 3/4/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/11/2024 Partial Inspection JOHN COLEMAN
ELECTRICAL-Rough 3/11/2024 Approved JOHN COLEMAN
HVAC-Rough 3/11/2024 Approved JOHN COLEMAN
Shower Pan 3/11/2024 Approved JOHN COLEMAN
Insulation 3/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Corrections Issued KIRK SANDERS
Insulation 3/18/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 3/18/2024 Approved KIRK SANDERS
Drywall Nailing 3/21/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/21/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/21/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/27/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/27/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 6/27/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 6/27/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 7/10/2024 Approved CHRISTOPHER ROJAS
Final 7/10/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 7/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 7/10/2024 Approved CHRISTOPHER ROJAS
Final 7/16/2024 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 8/2/2024 Approved CHRISTOPHER ROJAS
Final 8/2/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 8/2/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 8/2/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 8/2/2024 Approved CHRISTOPHER ROJAS
Smoke Detectors 8/2/2024 Approved CHRISTOPHER ROJAS