2970 N TYBURN ST 90039
Certificate Information: 2970 N TYBURN ST 90039
- Application / Permit
- 23016-20000-21567
- Plan Check / Job No.
- B23VN08724
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT IRREG SHAPED PORTION OF DETACHED GARAGE TO STORAGE ROOM. CONVERT REMAINING PORTION OF GARAGE AND REC ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 7/8/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/13/2023 | APPLICANT |
| Applicant returned to address corrections | 11/15/2023 | RAMA DABADGE |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 5/1/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 7/31/2023 | STEVEN WECHSLER |
| Address approval | Cleared | 8/3/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/3/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2023 | ADRIAN SANCHEZ |
| Public Works-Highway Ded. | Cleared | 4/17/2025 | VISHAL MANDALIA |
| Public Works-Open Permits | Cleared | 4/17/2025 | VISHAL MANDALIA |
| Public Works-Sewers | Cleared | 4/17/2025 | VISHAL MANDALIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/21/2024 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/2/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/17/2024 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/17/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/15/2024 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 5/22/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 5/22/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 5/23/2024 | Approved | JOSEPH MCGARRY |
| MERV13>=Rough | 5/23/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/5/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 6/5/2024 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 6/24/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/11/2024 | Partial Approval | THOMAS LOGRASSO |
| Final | 4/15/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/15/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| MERV13>=Final | 4/15/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 4/15/2025 | Approved | NICHOLAS LOPEZ |
| Final | 4/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 4/24/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 4/28/2025 | Approved | NICHOLAS LOPEZ |
| Final | 5/1/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 5/1/2025 | Approved | NICHOLAS LOPEZ |