7338-7340 W KYLE ST 91042

Certificate Information: 7338-7340 W KYLE ST 91042

Application / Permit
23016-20000-21515
Plan Check / Job No.
B23VN08697
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert existing attached garage into new ADU per 65852.2(e)(1)(A).
Permit Issued
Issued on 11/13/2023
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 JOHNPAUL ISIP
Corrections Issued 7/9/2023 JOHNPAUL ISIP
Applicant returned to address corrections 9/29/2023 CAROLEAN BASMA
Applicant returned to address corrections 10/4/2023 JOHNPAUL ISIP
Plan Check Approved 11/6/2023 JOHNPAUL ISIP
Issued 11/13/2023 APPLICANT
CofO in Progress 7/10/2025 MICHEL ABAJAN
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/11/2023 TAL SHEMEN
Sewer availability Cleared 7/11/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 11/1/2023 MARKOS PEREZ-BRAN

Contact Information

Contractor Coasis Construction & Remodeling Inc; Lic. No.: 1099824-B 9532 TOPANGA CANYON BLVD      CHATSWORTH, CA 91311
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/18/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 1/18/2024 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 1/25/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 2/13/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/17/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 6/17/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 6/17/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 6/17/2024 Not Ready for Inspection WILLIAM WREN
Rough-Elec/Plmb/HVAC 6/17/2024 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 6/27/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 6/27/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 6/27/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 6/27/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/3/2024 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 7/3/2024 Approved WILLIAM WREN
Green Building Rough 7/3/2024 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 8/2/2024 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 8/2/2024 Approved MATTHEW NELSON
Green Building Rough 8/2/2024 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 8/2/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 8/2/2024 Approved MATTHEW NELSON
Pre-Inspection 8/13/2024 Partial Inspection WILLIAM WREN
BUILDING-Rough-Frame 3/6/2025 Approved WILLIAM WREN
Green Building Rough 3/6/2025 Approved WILLIAM WREN
HVAC-Rough 3/6/2025 Approved WILLIAM WREN
PLUMBING-Rough 3/6/2025 Approved WILLIAM WREN
Insulation 3/17/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/17/2025 Approved MICHEL ABAJAN
Drywall Nailing 3/24/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 3/24/2025 Approved WILLIAM WREN
Shower Pan 3/24/2025 Approved WILLIAM WREN
ELECTRICAL-Final 7/2/2025 Approved MICHEL ABAJAN
Final 7/2/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 7/2/2025 Approved MICHEL ABAJAN
HVAC-Final 7/2/2025 Approved MICHEL ABAJAN
PLUMBING-Final 7/2/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/2/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/9/2025 Approved MICHEL ABAJAN
Final 7/9/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 7/9/2025 Approved MICHEL ABAJAN
PLUMBING-Final 7/9/2025 Approved MICHEL ABAJAN