7338-7340 W KYLE ST 91042
Certificate Information: 7338-7340 W KYLE ST 91042
- Application / Permit
- 23016-20000-21515
- Plan Check / Job No.
- B23VN08697
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached garage into new ADU per 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/13/2023
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | JOHNPAUL ISIP |
| Corrections Issued | 7/9/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 9/29/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/4/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 11/6/2023 | JOHNPAUL ISIP |
| Issued | 11/13/2023 | APPLICANT |
| CofO in Progress | 7/10/2025 | MICHEL ABAJAN |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/11/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Coasis Construction & Remodeling Inc; Lic. No.: 1099824-B | 9532 TOPANGA CANYON BLVD CHATSWORTH, CA 91311 |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 1/18/2024 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 1/25/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/13/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/17/2024 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 6/17/2024 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 6/17/2024 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 6/17/2024 | Not Ready for Inspection | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 6/17/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/27/2024 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 6/27/2024 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 6/27/2024 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 6/27/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/3/2024 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 7/3/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 7/3/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/2/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/2/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/2/2024 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 8/2/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/2/2024 | Approved | MATTHEW NELSON |
| Pre-Inspection | 8/13/2024 | Partial Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/6/2025 | Approved | WILLIAM WREN |
| Green Building Rough | 3/6/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 3/6/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 3/6/2025 | Approved | WILLIAM WREN |
| Insulation | 3/17/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/17/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/24/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/24/2025 | Approved | WILLIAM WREN |
| Shower Pan | 3/24/2025 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 7/2/2025 | Approved | MICHEL ABAJAN |
| Final | 7/2/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/2/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/2/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/2/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/2/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/9/2025 | Approved | MICHEL ABAJAN |
| Final | 7/9/2025 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 7/9/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/9/2025 | Approved | MICHEL ABAJAN |