8515-8517 N TERHUNE AVE 91352
Certificate Information: 8515-8517 N TERHUNE AVE 91352
- Application / Permit
- 23016-20000-21480
- Plan Check / Job No.
- B23VN08675
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE INTO ( N) SB9 UNIIT & ADD COV'D PARKING (5'-6" X 36') **ePlan **
- Permit Issued
- Issued on 11/1/2023
- Issuing Office
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/8/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/12/2023 | STEVEN KIM |
| Applicant returned to address corrections | 9/13/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/16/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/17/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/26/2023 | NILOOFAR MEHRAIN |
| Issued | 11/1/2023 | APPLICANT |
| CofO in Progress | 8/26/2024 | DAVID ANDERSON |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 7/25/2023 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 8/22/2023 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 9/4/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/29/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 1/8/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 1/9/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 1/18/2024 | Approved | DAVID ANDERSON |
| Sewer | 1/18/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/9/2024 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 2/9/2024 | Order to Comply Issued | WILLIAM WREN |
| HVAC-Rough | 2/9/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/13/2024 | Approved | DAVID ANDERSON |
| Insulation | 2/20/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/20/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/23/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 2/23/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/28/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | DAVID ANDERSON |
| Final | 6/10/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 6/10/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/10/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 6/10/2024 | Approved | DAVID ANDERSON |
| Final | 6/11/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 8/23/2024 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 9/5/2024 | Approved | DAVID ANDERSON |