8515-8517 N TERHUNE AVE 91352

Certificate Information: 8515-8517 N TERHUNE AVE 91352

Application / Permit
23016-20000-21480
Plan Check / Job No.
B23VN08675
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE INTO ( N) SB9 UNIIT & ADD COV'D PARKING (5'-6" X 36') **ePlan **
Permit Issued
Issued on 11/1/2023
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 NILOOFAR MEHRAIN
Corrections Issued 7/8/2023 NILOOFAR MEHRAIN
Quality Review Completed 7/12/2023 STEVEN KIM
Applicant returned to address corrections 9/13/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/16/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/17/2023 NILOOFAR MEHRAIN
Plan Check Approved 10/26/2023 NILOOFAR MEHRAIN
Issued 11/1/2023 APPLICANT
CofO in Progress 8/26/2024 DAVID ANDERSON
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/24/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 7/24/2023 NIKKI ZULUETA
Sewer availability Cleared 7/25/2023 NIKKI ZULUETA
Senate Bill 9 Cleared 8/22/2023 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 9/4/2023 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2023 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 1/8/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 1/9/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved DAVID ANDERSON
PLUMBING-Rough 1/18/2024 Approved DAVID ANDERSON
Sewer 1/18/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/9/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 2/9/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 2/9/2024 Order to Comply Issued WILLIAM WREN
HVAC-Rough 2/9/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 2/13/2024 Approved DAVID ANDERSON
Insulation 2/20/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/20/2024 Approved DAVID ANDERSON
Drywall Nailing 2/23/2024 Approved DAVID ANDERSON
Shower Pan 2/23/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/28/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 6/10/2024 Approved DAVID ANDERSON
Final 6/10/2024 Not Ready for Inspection DAVID ANDERSON
Green Building Final 6/10/2024 Approved DAVID ANDERSON
Green Building Rough 6/10/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 6/10/2024 Approved DAVID ANDERSON
Final 6/11/2024 Corrections Issued DAVID ANDERSON
Final 8/23/2024 OK to Issue CofO DAVID ANDERSON
Service/Power Release 9/5/2024 Approved DAVID ANDERSON