- REMODEL (E) SFD AND REFRAME PORTION OF (E) ROOF PER ENGINEERING.
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/26/2024
Permit Application Status History
| Submitted | 6/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/3/2023 | APPLICANT |
| Corrections Issued | 7/4/2023 | ARTIN ZARUKIAN |
| Plan Check Approved | 7/7/2023 | LUISANGEL VALENZUELA |
| Issued | 7/7/2023 | APPLICANT |
| Permit Finaled | 1/26/2024 | BOBBY KEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/7/2023 | JONATHAN HOM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/31/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 9/5/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/8/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Partial Approval | BOBBY KEY |
| Gas Test | 9/8/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/12/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 9/20/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 9/20/2023 | Approved | BOBBY KEY |
| Shower Pan | 9/21/2023 | Approved | KENNETH NAGLE |
| Deputy Other (see comments) | 9/25/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | BOBBY KEY |
| Insulation | 9/29/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 9/29/2023 | Partial Approval | BOBBY KEY |
| Insulation | 10/2/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 10/6/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/10/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/13/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/13/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 1/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 1/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Service/Power Release | 1/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Smoke Detectors | 1/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 1/23/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 1/23/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/26/2024 | Approved | BOBBY KEY |
| Final | 1/26/2024 | Permit Finaled | BOBBY KEY |
| PLUMBING-Final | 1/26/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | BOBBY KEY |