7931 S STEWART AVE 90045

Certificate Information: 7931 S STEWART AVE 90045

Application / Permit
23016-20000-21424
Plan Check / Job No.
B23VN08651
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD AND REFRAME PORTION OF (E) ROOF PER ENGINEERING.
Permit Issued
Issued on 7/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/26/2024

Permit Application Status History

Submitted 6/29/2023 APPLICANT
Assigned to Plan Check Engineer 7/3/2023 ARTIN ZARUKIAN
Building Plans Picked Up 7/3/2023 APPLICANT
Corrections Issued 7/4/2023 ARTIN ZARUKIAN
Plan Check Approved 7/7/2023 LUISANGEL VALENZUELA
Issued 7/7/2023 APPLICANT
Permit Finaled 1/26/2024 BOBBY KEY

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/7/2023 JONATHAN HOM

Contact Information

Contractor Owner-Builder       ,
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2023 Approved BOBBY KEY
ELECTRICAL-Rough 9/5/2023 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 9/8/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval BOBBY KEY
Gas Test 9/8/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 9/8/2023 Corrections Issued BOBBY KEY
HVAC-Rough 9/12/2023 Approved BOBBY KEY
PLUMBING-Rough 9/12/2023 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 9/20/2023 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 9/20/2023 Approved BOBBY KEY
Shower Pan 9/21/2023 Approved KENNETH NAGLE
Deputy Other (see comments) 9/25/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 9/29/2023 Approved BOBBY KEY
Insulation 9/29/2023 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 9/29/2023 Partial Approval BOBBY KEY
Insulation 10/2/2023 Corrections Issued BOBBY KEY
Insulation 10/6/2023 Approved TEMISTOCLES CAAL
Drywall Nailing 10/10/2023 Approved TEMISTOCLES CAAL
Drywall Nailing 10/13/2023 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 10/13/2023 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 1/18/2024 Corrections Issued TEMISTOCLES CAAL
Final 1/18/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 1/18/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 1/18/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Not Ready TEMISTOCLES CAAL
Service/Power Release 1/18/2024 Not Ready for Inspection TEMISTOCLES CAAL
Smoke Detectors 1/18/2024 Corrections Issued TEMISTOCLES CAAL
Final 1/23/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 1/23/2024 Approved BOBBY KEY
ELECTRICAL-Final 1/26/2024 Approved BOBBY KEY
Final 1/26/2024 Permit Finaled BOBBY KEY
PLUMBING-Final 1/26/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Approved BOBBY KEY