924-924 1/2 E 46TH ST 90011

Certificate Information: 924-924 1/2 E 46TH ST 90011

Application / Permit
23016-20000-21031
Plan Check / Job No.
B23VN08499
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Covert (E) Storage & Laundry Areas at the 1st Floor to an attached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(C) . NO SQFT ADDED. NO STRUCTURE WORK
Permit Issued
Issued on 1/24/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2023 APPLICANT
Assigned to Plan Check Engineer 6/30/2023 ALFREDO JARA
Corrections Issued 7/2/2023 ALFREDO JARA
Applicant returned to address corrections 12/28/2023 GEORGE ALVAREZ
Applicant returned to address corrections 1/18/2024 KHUONG TRUONG
Issued 1/24/2024 APPLICANT
CofO in Progress 6/26/2025 ALEJANDRO DE ARTOLA
Permit Finaled 6/29/2025 DEROLD HAUFF
CofO Issued 6/29/2025 DEROLD HAUFF
Permit Finaled 6/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/19/2023 WALLIE JONG
Roof/Waste drainage to street Cleared 7/19/2023 WALLIE JONG
Sewer availability Cleared 7/19/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/27/2023 WALLIE JONG
Tenant Habitability Plan Cleared 8/3/2023 RICARDO BOHORQUEZ
Construction near power lines Cleared 12/19/2023 TINA MIRANDA
Miscellaneous Cleared 1/18/2024 GEORGE ALVAREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 2/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/22/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 3/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 3/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 4/29/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 5/8/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 5/8/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/14/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/23/2024 Approved ALEJANDRO DE ARTOLA
Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 6/24/2024 Approved ALEJANDRO DE ARTOLA
Final 7/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/26/2024 Approved ALEJANDRO DE ARTOLA
Final 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 9/10/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/21/2025 Approved MICHAEL LEWIS
Wood Frame 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 2/5/2025 Approved ALEJANDRO DE ARTOLA
Insulation 2/7/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/7/2025 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 3/3/2025 Approved ALEJANDRO DE ARTOLA
Final 6/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/25/2025 OK to Issue CofO ALEJANDRO DE ARTOLA