4429 N LENNOX AVE 91423
Certificate Information: 4429 N LENNOX AVE 91423
- Application / Permit
- 23016-20000-20931
- Plan Check / Job No.
- B23VN08433
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 6'X8' PANTRY/LAUNDRY RM & 4'-8"X30' PATIO COVER ADDN. INT/EXT REMODEL - DEMO EX INT WALLS BETWEEN KITCHEN/DINING/LIVING RM TO CREATE OPEN ROOM & REMODEL KITCHEN. ENLARGE & REMODEL EX BATHRM. ADD ONE SKYLIGHT. CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 6/26/2023 | ALFRED RAMIREZ |
| No Progress | 9/16/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/10/2023 | ALEC MOUSAKHANIAN |
| Issued | 10/18/2023 | APPLICANT |
| CofO in Progress | 12/14/2024 | MISAEL ESPARZA |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
| CofO Issued | 1/7/2025 | RUBEN SALAS |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/21/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2023 | RYAN KIM |
Contact Information
| Architect | Benavidez,, Alexis; Lic. No.: C39253 | 15948 DEVONSHIRE ST GRANADA HILLS, CA 91344 |
| Contractor | Donaldson John R Construction Inc; Lic. No.: 641405-B | 14320 VENTURA BLVD 610 SHERMAN OAKS, CA 91423 |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2024 | Approved | MISAEL ESPARZA |
| Gas Test | 6/4/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 6/4/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/5/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 6/5/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/7/2024 | Partial Approval | MISAEL ESPARZA |
| Insulation | 7/1/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/12/2024 | Approved | JUAN VALENZUELA |
| Green Building Rough | 7/12/2024 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/4/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/4/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/4/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 12/4/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 12/4/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/4/2024 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/4/2024 | Approved | MISAEL ESPARZA |
| Final | 12/9/2024 | OK to Issue CofO | MISAEL ESPARZA |