18137 W PARTHENIA ST 91325
Certificate Information: 18137 W PARTHENIA ST 91325
- Application / Permit
- 23016-20000-20680
- Plan Check / Job No.
- B23VN08295
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- CHANGE OF USE FROM OFFICE/MANUFACTURING TO MEDICAL OFFICES: DEMO & ADD NON-BEARING PARTITIONS; RE-STRIPE PARKING LOT **ePlan **
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Current Status
- CofO Corrected on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/8/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/18/2023 | STEVEN KIM |
| Applicant returned to address corrections | 8/14/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/6/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/12/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/26/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/4/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/20/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/4/2024 | NILOOFAR MEHRAIN |
| Issued | 6/10/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | DEANDRE HOFFMAN |
| CofO in Progress | 2/5/2025 | VERN CUIZON |
| CofO Issued-Status Void | 2/5/2025 | JEFFREY DURAN |
| Permit Finaled-Status Void | 2/5/2025 | JEFFREY DURAN |
| Re-Activate Permit | 3/11/2025 | JEFFREY DURAN |
| Permit Finaled | 3/11/2025 | JEFFREY DURAN |
| CofO Corrected | 3/11/2025 | JEFFREY DURAN |
| Permit Finaled | 3/11/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Driveway location | Cleared | 7/17/2023 | MIGUEL CRISOSTOMO |
| Internal circulation | Cleared | 7/17/2023 | MIGUEL CRISOSTOMO |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/19/2023 | TAL SHEMEN |
| Public Works-Highway Ded. | Cleared | 7/19/2023 | TAL SHEMEN |
| Public Works-Open Permits | Cleared | 7/19/2023 | TAL SHEMEN |
| Public Works-Sewers | Cleared | 7/19/2023 | TAL SHEMEN |
| "Q" conditions | Cleared | 7/21/2023 | NATHAN ROMINE |
| Prkng lot landscape/Water mgmt | Cleared | 7/21/2023 | NATHAN ROMINE |
| Green Code | Cleared | 8/11/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 2/15/2024 | Rosendo Medina |
Contact Information
| Contractor | Purple Construction Inc; Lic. No.: 1020672-B | , |
| Engineer | Yeh,, Ming Yang; Lic. No.: S2587 | 1613 CHELSEA ROAD #233 SAN MARINO, CA 91108 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 6/21/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/21/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 7/3/2024 | Conditional Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 7/9/2024 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 7/9/2024 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 8/7/2024 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/14/2024 | Approved | DEANDRE HOFFMAN |
| Insulation | 11/14/2024 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 11/21/2024 | Approved | DEANDRE HOFFMAN |
| T-Bar Ceiling | 12/16/2024 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 1/2/2025 | Partial Approval | GREGORY POMISH |
| Final | 1/15/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Final | 1/15/2025 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 1/15/2025 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 1/15/2025 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 1/15/2025 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 1/15/2025 | Approved | DEANDRE HOFFMAN |
| Final | 1/28/2025 | No Access for Inspection | DEANDRE HOFFMAN |
| Final | 1/30/2025 | OK to Issue CofO | DEANDRE HOFFMAN |