18040 W CHATSWORTH ST 91344
Certificate Information: 18040 W CHATSWORTH ST 91344
- Application / Permit
- 23016-20000-20635
- Plan Check / Job No.
- B23VN08278
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT TO (E) RETAIL SPACE: DEMO/ADD NON-BEARING PARTITION WALLS, CREATE (N) OPENING IN (E) WALL, ADD MECHANICAL UNITS AT ROOF ** ePlan**
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/28/2024
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/2/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/7/2023 | STEVEN KIM |
| Applicant returned to address corrections | 8/8/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/23/2023 | NILOOFAR MEHRAIN |
| Issued | 9/21/2023 | APPLICANT |
| Permit Finaled | 3/27/2024 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/12/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 7/12/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 7/12/2023 | DANIEL CORONADO |
| Specific Plan | Cleared | 7/18/2023 | CORREY KITCHENS |
| ZI | Cleared | 7/18/2023 | CORREY KITCHENS |
| Green Code | Cleared | 8/1/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/7/2023 | Rosendo Medina |
Contact Information
| Architect | Winkler,, Page; Lic. No.: C31839 | 14558 LUNA MEDIA SAN DIEGO, CA 92127 |
| Contractor | Ryan Contractors Inc; Lic. No.: 976882-B | , |
| Engineer | Troxell,, David; Lic. No.: S4994 | 8406 N 86TH WY SCOTTSDALE, AZ 85258 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/9/2023 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 11/20/2023 | Corrections Issued | STEVEN LEVITT |
| Footing/Foundation/Slab | 1/3/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 1/17/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 1/18/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 1/23/2024 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 1/23/2024 | Approved | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 1/24/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Special/Order Compliance | 1/24/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 2/7/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Final | 2/7/2024 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 2/7/2024 | Approved | DEANDRE HOFFMAN |
| Final | 2/12/2024 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 2/21/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 2/21/2024 | Partial Inspection | MELVIN GIRTON |
| Final | 2/28/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 2/28/2024 | Partial Inspection | MELVIN GIRTON |
| Final | 3/27/2024 | Permit Finaled | DEANDRE HOFFMAN |