4855-4857 N LEDGE AVE 91601
Certificate Information: 4855-4857 N LEDGE AVE 91601
- Application / Permit
- 23016-20000-20541
- Plan Check / Job No.
- B23VN08220
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTACHED GARAGE AND PORTION OF SINGLE FAMILY DWELLING INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 6/28/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/10/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/13/2023 | ISIS ARGUETA |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 10/15/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
| CofO Issued | 10/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/3/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/20/2023 | Conditional Approval | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 1/2/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/4/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 2/7/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 2/15/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 2/15/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/26/2024 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/26/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/8/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/8/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/8/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/17/2024 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/23/2024 | Conditional Approval | SALVADOR MARTINEZ |
| Special/Order Compliance | 4/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 5/3/2024 | Approved | LEONARD ROSS II |
| Insulation | 5/3/2024 | Conditional Approval | LEONARD ROSS II |
| Interior/Exterior Lathing | 5/30/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/12/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/17/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/17/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 9/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 10/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/2/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 10/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/11/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 10/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |