960-962 N TIGERTAIL ROAD 90049

Certificate Information: 960-962 N TIGERTAIL ROAD 90049

Application / Permit
23016-20000-20433
Plan Check / Job No.
B23VN08170
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX 81'-8"X10'-3" NON-HABITABLE BASEMENT FLOOR INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) . ALL WORK PER WFPP. " COMPLY WITH DEPARTMENT ORDER effective date 02/15/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/25/2023
Issuing Office
Current Status
CofO Issued on 1/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 HAYATO TSUCHIYA
Corrections Issued 6/24/2023 HAYATO TSUCHIYA
Building Plans Picked Up 7/6/2023 APPLICANT
Applicant returned to address corrections 10/12/2023 LUISANGEL VALENZUELA
Plan Check Approved 10/20/2023 DANIEL ABRAMYAN
Issued 10/25/2023 APPLICANT
CofO in Progress 12/17/2024 ANDREW BEELI
Permit Finaled 1/30/2025 CLAUDIO MORENO
CofO Issued 1/30/2025 CLAUDIO MORENO
Permit Finaled 1/30/2025 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 8/30/2023 JASON NG
BHO/Hillside ordinance Cleared 8/30/2023 JASON NG
BHO/Hillside ordinance Cleared 8/30/2023 JASON NG
BHO/Hillside ordinance Cleared 8/30/2023 JASON NG
BHO/Hillside ordinance Cleared 8/30/2023 JASON NG
BHO/Hillside ordinance Cleared 8/30/2023 JASON NG
Sewer availability Cleared 8/30/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/31/2023 JASON NG
Hydrant and Access approval Cleared 9/29/2023 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2023 Not Ready for Inspection ANDREW BEELI
BUILDING-Rough-Frame 2/1/2024 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 2/1/2024 Corrections Issued ANDREW BEELI
HVAC-Rough 2/1/2024 Corrections Issued ANDREW BEELI
PLUMBING-Rough 2/1/2024 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 3/20/2024 Not Ready for Inspection ANDREW BEELI
Wood Frame 3/20/2024 Corrections Issued ANDREW BEELI
Pre-Inspection 3/28/2024 Corrections Issued ANDREW BEELI
Pre-Inspection 4/23/2024 Corrections Issued ANDREW BEELI
Pre-Inspection 5/1/2024 Corrections Issued ANDREW BEELI
Pre-Inspection 5/3/2024 Not Ready for Inspection ANDREW BEELI
Pre-Inspection 5/7/2024 Not Ready for Inspection ANDREW BEELI
Pre-Inspection 6/12/2024 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 7/5/2024 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 7/5/2024 Corrections Issued ANDREW BEELI
ELECTRICAL-Final 7/22/2024 Corrections Issued ANDREW BEELI
PLUMBING-Final 7/22/2024 Not Ready for Inspection ANDREW BEELI
Wood Frame 7/22/2024 Not Ready for Inspection ANDREW BEELI
Insulation 7/30/2024 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 7/30/2024 Corrections Issued ANDREW BEELI
Insulation 8/8/2024 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 8/8/2024 Not Ready for Inspection ANDREW BEELI
BUILDING-Rough-Frame 8/13/2024 Not Ready for Inspection ANDREW BEELI
Gas Test 8/13/2024 Approved ANDREW BEELI
Insulation 8/13/2024 Conditional Approval ANDREW BEELI
Rough-Elec/Plmb/HVAC 8/13/2024 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 8/19/2024 Partial Approval ANDREW BEELI
Drywall Nailing 8/22/2024 Not Ready for Inspection ANDREW BEELI
Shower Pan 8/22/2024 Not Ready for Inspection ANDREW BEELI
Drywall Nailing 8/27/2024 Approved ANDREW BEELI
Shower Pan 8/27/2024 Approved ANDREW BEELI
BUILDING-Rough-Frame 11/7/2024 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Final 11/7/2024 Not Ready for Inspection ANDREW BEELI
Final 11/7/2024 Not Ready for Inspection ANDREW BEELI
HVAC-Final 11/7/2024 Not Ready for Inspection ANDREW BEELI
PLUMBING-Final 11/7/2024 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 11/7/2024 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 11/22/2024 Approved ANDREW BEELI
ELECTRICAL-Final 11/22/2024 Approved ANDREW BEELI
Final 11/22/2024 Partial Approval ANDREW BEELI
HVAC-Final 11/22/2024 Approved ANDREW BEELI
PLUMBING-Final 11/22/2024 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved ANDREW BEELI
Smoke Detectors 11/22/2024 Approved ANDREW BEELI
Final 12/13/2024 Partial Approval ANDREW BEELI
Final 12/17/2024 OK to Issue CofO ANDREW BEELI