13466 N FENTON AVE 91342

Certificate Information: 13466 N FENTON AVE 91342

Application / Permit
23016-20000-20319
Plan Check / Job No.
B23VN08104
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) 2-CAR GARAGE TO CONVERT TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/10/2023
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 SERGIO MUNIZ
Corrections Issued 6/26/2023 SERGIO MUNIZ
Building Plans Picked Up 6/27/2023 APPLICANT
Plan Check Approved 7/5/2023 MOHAMMAD ESMAILI
Issued 7/10/2023 APPLICANT
CofO in Progress 4/21/2026 RAUL OLAGI
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2023 ROMAN GUTIERREZ
Sewer availability Cleared 6/30/2023 ROMAN GUTIERREZ
ZA Case Cleared 6/30/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 7/3/2023 ROMAN GUTIERREZ
Hold Cleared 6/17/2024 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2024 Partial Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 9/18/2024 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/5/2024 Partial Inspection KEVIN BERBERYAN
Sewer 11/5/2024 Approved KEVIN BERBERYAN
Underground Mechanical 11/5/2024 Approved KEVIN BERBERYAN
Wood Frame 3/11/2025 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 3/27/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 3/27/2025 Corrections Issued KEVIN BERBERYAN
Insulation 5/30/2025 No Access for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 6/2/2025 Corrections Issued LOUIS ESCOTO
Insulation 6/2/2025 Corrections Issued LOUIS ESCOTO
Rough-Elec/Plmb/HVAC 6/2/2025 Corrections Issued LOUIS ESCOTO
Insulation 6/9/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 6/30/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 9/10/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 4/14/2026 Approved KEVIN BERBERYAN
Final 4/14/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 4/14/2026 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 4/14/2026 Approved KEVIN BERBERYAN
PLUMBING-Final 4/14/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 4/14/2026 Approved KEVIN BERBERYAN
Final 4/20/2026 OK to Issue CofO RAUL OLAGI
Green Building Final 4/20/2026 Approved RAUL OLAGI