108 E PARK PL 1-3 90291
Certificate Information: 108 E PARK PL 1-3 90291
- Application / Permit
- 23016-20000-20008
- Plan Check / Job No.
- B23VN08012
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT REC RM/STORAGE TO ACCESSORY DWELLING UNIT (600 SF) PER GC 66323(a)(3)
- Permit Issued
- Issued on 12/10/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | JESSE ARELLANO |
| Corrections Issued | 6/24/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Applicant returned to address corrections | 12/4/2025 | AMY GUEVARRA |
| Plan Check Approved | 12/10/2025 | AMY GUEVARRA |
| Issued | 12/10/2025 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/28/2023 | SPENCER WEJROWSKI |
| ZI | Cleared | 7/28/2023 | SPENCER WEJROWSKI |
| Address approval | Cleared | 7/31/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | JASON NG |
| Sewer availability | Cleared | 8/23/2023 | JASON NG |
| Coastal Zone | Cleared | 9/24/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 9/24/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 9/24/2025 | DANIEL CORONADO |
| ZI | Cleared | 9/24/2025 | DANIEL CORONADO |
Contact Information
| Contractor | Locali Builders Inc; Lic. No.: 1110807-B | 23705 VANOWEN ST 234 WEST HILLS, CA 91307 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 12/23/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 1/8/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 2/9/2026 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 2/9/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/10/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/10/2026 | Corrections Issued | RUBEN RIVAS |
| HVAC-Rough | 3/10/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/10/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/19/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/19/2026 | Approved | RUBEN RIVAS |
| HVAC-Rough | 3/19/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/19/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 3/26/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/26/2026 | Approved | RUBEN RIVAS |
| Insulation | 4/7/2026 | Approved | RUBEN RIVAS |
| Light Gage Steel Frame | 4/13/2026 | Approved | RUBEN RIVAS |
| Shower Pan | 4/13/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 4/23/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/23/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 5/27/2026 | Approved | RUBEN RIVAS |