709 E 92ND ST 90002
Certificate Information: 709 E 92ND ST 90002
- Application / Permit
- 23016-20000-19979
- Plan Check / Job No.
- B23VN07998
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION AT THE REAR PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2023 | ISIS ARGUETA |
| Corrections Issued | 6/27/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 12/7/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 12/8/2023 | NEHEMIAS RAMOS |
| Issued | 12/8/2023 | APPLICANT |
| CofO in Progress | 1/21/2025 | JOHN QUINTANILLA |
| CofO Issued | 1/27/2025 | DEROLD HAUFF |
| Permit Finaled | 1/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | NEIL TUANO |
| Sewer availability | Cleared | 8/1/2023 | NEIL TUANO |
| ZA Case | Cleared | 8/17/2023 | NOAH MCCOY |
| Construction near power lines | Cleared | 12/7/2023 | EDGAR PASCUA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/6/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 9/6/2024 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/6/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Sewer | 9/6/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 9/6/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/23/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/23/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/23/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/23/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 9/23/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Final | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Green Building Final | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Final | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 12/10/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/27/2024 | Approved | JOHN QUINTANILLA |
| Final | 12/27/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/27/2024 | Approved | JOHN QUINTANILLA |
| Green Building Final | 12/27/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 12/27/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 12/27/2024 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2024 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 12/27/2024 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 12/31/2024 | Approved | JOHN QUINTANILLA |
| Final | 1/17/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| Service/Power Release | 1/17/2025 | Approved | JOHN QUINTANILLA |