9724 N MERCEDES AVE 91331

Certificate Information: 9724 N MERCEDES AVE 91331

Application / Permit
23016-20000-19880
Plan Check / Job No.
B23VN07938
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage into one story detached ADU per LAMC 12.22 A.33(c) and (d). Work per engineering.
Permit Issued
Issued on 8/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 RAMA DABADGE
Corrections Issued 6/26/2023 RAMA DABADGE
Building Plans Picked Up 6/28/2023 APPLICANT
Plan Check Approved 7/12/2023 ISIS ARGUETA
Issued 8/7/2023 APPLICANT
CofO in Progress 11/21/2023 MICHEL ABAJAN
Permit Finaled 2/14/2024 RUBEN SALAS
CofO Issued 2/14/2024 RUBEN SALAS
Permit Finaled 2/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2023 NIKKI ZULUETA
Sewer availability Cleared 6/30/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 7/5/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/18/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 8/21/2023 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 8/23/2023 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/28/2023 Approved MICHEL ABAJAN
Underground Mechanical 8/28/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/6/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 9/6/2023 Approved MICHEL ABAJAN
Green Building Rough 9/6/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/6/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/6/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 9/8/2023 Approved MICHEL ABAJAN
METHANE-Rough 9/8/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/8/2023 Approved MICHEL ABAJAN
Insulation 9/12/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/12/2023 Approved MICHEL ABAJAN
Drywall Nailing 9/19/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/17/2023 Approved MICHEL ABAJAN
HVAC-Final 11/17/2023 Approved MICHEL ABAJAN
PLUMBING-Final 11/17/2023 Approved MICHEL ABAJAN
Final 11/20/2023 OK to Issue CofO MICHEL ABAJAN
PLUMBING-Final 11/20/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/20/2023 Approved MICHEL ABAJAN