8407 N FALLBROOK AVE 100,140-150 91304
Certificate Information: 8407 N FALLBROOK AVE 100,140-150 91304
- Application / Permit
- 23016-20000-19837
- Plan Check / Job No.
- B23VN07925
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePlan ***PROPOSED TENANT IMPROVEMENT AND CHANGE OF USE TO OFFICE AND LAB BUILDING IN UNITS 100, 140 AND 150
- Permit Issued
- Issued on 10/23/2023
- Issuing Office
- Current Status
- CofO Issued on 8/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | SINA KHOSRAVI |
| Corrections Issued | 6/28/2023 | SINA KHOSRAVI |
| Quality Review Completed | 7/7/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/16/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 9/15/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/3/2023 | SINA KHOSRAVI |
| Plan Check Approved | 10/12/2023 | SINA KHOSRAVI |
| Plan Check Approved | 10/17/2023 | SINA KHOSRAVI |
| Issued | 10/23/2023 | APPLICANT |
| TCO Issued (Expire Date: 05-20-2025) | 11/21/2024 | JEFFREY DURAN |
| TCO Issued (Expire Date: 10-19-2025) | 4/22/2025 | RICKEY JACKSON |
| CofO in Progress | 8/20/2025 | DEANDRE HOFFMAN |
| Permit Finaled | 8/22/2025 | JEFFREY DURAN |
| CofO Issued | 8/22/2025 | JEFFREY DURAN |
| Permit Finaled | 8/22/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/13/2023 | YINGSHI HUANG |
| "T" removal | Cleared | 7/13/2023 | YINGSHI HUANG |
| Green Code | Cleared | 8/8/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/17/2023 | Hernan Arreola |
| Sewer availability | Cleared | 9/23/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | CARLOS AGUILERA |
Contact Information
| Architect | Dwyer,, Susan M; Lic. No.: NA33724 | , |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
| Engineer | Bishoff,, Ryam William; Lic. No.: S6250 | 9252 DALTON CIRCLE WESTMINSTER, CA 92683 |
| Engineer | Melo,, Edgard; Lic. No.: C80534 | 700 S FLOWER ST 1200 LOS ANGELES, CA 90017 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 11/22/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 11/30/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 12/5/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 12/6/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 12/7/2023 | Conditional Approval | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 12/8/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Grading | 12/8/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Grading | 12/19/2023 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 12/21/2023 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/3/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 1/4/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 1/8/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 1/10/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 1/10/2024 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 1/11/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 1/17/2024 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 1/31/2024 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 1/31/2024 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 2/6/2024 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 2/21/2024 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 4/2/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 4/11/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Wood Construction | 4/16/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 4/24/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 4/24/2024 | Partial Approval | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 5/3/2024 | Partial Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 5/16/2024 | Approved | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 6/13/2024 | Conditional Approval | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/20/2024 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 6/24/2024 | Conditional Approval | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/24/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/25/2024 | Approved | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 6/27/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Pre-Inspection | 7/15/2024 | Not Ready for Inspection | GREGORY POMISH |
| Pre-Inspection | 7/16/2024 | Partial Inspection | GREGORY POMISH |
| Deputy Drilled-In Anchors | 7/22/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Special/Order Compliance | 7/22/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 9/18/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 2/14/2025 | Not Ready for Inspection | GREGORY POMISH |
| Special/Order Compliance | 4/22/2025 | No Access for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Final | 6/27/2025 | Partial Inspection | GREGORY POMISH |
| Green Building Final | 6/27/2025 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 6/27/2025 | Approved | GREGORY POMISH |
| Final | 8/20/2025 | OK to Issue CofO | DEANDRE HOFFMAN |