6923 N AMIGO AVE 91335

Certificate Information: 6923 N AMIGO AVE 91335

Application / Permit
23016-20000-19781
Plan Check / Job No.
B23VN07896
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 12'-10" X 18'-8" DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT (214 S.F ) PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP.
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 8/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/21/2023 MIROOSH KHACHATOORIAN
Corrections Issued 6/22/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/7/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 7/19/2023 ISIS ARGUETA
Plan Check Approved 7/28/2023 ALEC MOUSAKHANIAN
Issued 8/31/2023 APPLICANT
CofO in Progress 6/5/2024 JEFFREY BULL
Permit Finaled 8/8/2024 JOHN JANSON
CofO Issued 8/8/2024 JOHN JANSON
Permit Finaled 8/8/2024 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 7/5/2023 JAZMIN ROQUE
ZI Cleared 7/5/2023 JAZMIN ROQUE
Address approval Cleared 7/17/2023 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 7/17/2023 JOSEPH RHYU
Sewer availability Cleared 7/17/2023 JOSEPH RHYU

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/19/2023 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 10/19/2023 Approved JEFFREY BULL
PLUMBING-Rough 11/1/2023 Partial Approval JEFFREY BULL
Sewer 11/1/2023 Not Ready for Inspection JEFFREY BULL
Special/Order Compliance 11/1/2023 Corrections Issued JEFFREY BULL
PLUMBING-Rough 11/15/2023 Partial Approval JEFFREY BULL
Sewer 12/14/2023 Partial Approval MORRIS JACKSON
Sewer 12/20/2023 Approved JEFFREY BULL
Deputy Drilled-In Anchors 2/2/2024 Conditional Approval JEFFREY HARTLINE
ELECTRICAL-Rough 2/7/2024 Partial Approval JEFFREY BULL
Footing/Foundation/Slab 2/7/2024 Approved JEFFREY BULL
Deputy Other (see comments) 3/7/2024 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 3/8/2024 No Access for Inspection JEFFREY BULL
Green Building Rough 3/8/2024 No Access for Inspection JEFFREY BULL
Wood Frame 3/8/2024 No Access for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Approved JEFFREY BULL
Green Building Rough 3/12/2024 Not Ready for Inspection JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 3/15/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 4/3/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 4/3/2024 Approved JEFFREY BULL
Green Building Rough 4/3/2024 Approved JEFFREY BULL
PLUMBING-Rough 4/3/2024 Approved JEFFREY BULL
Insulation 4/5/2024 Approved JEFFREY BULL
Drywall Nailing 4/19/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 4/19/2024 Approved JEFFREY BULL
Shower Pan 4/19/2024 Approved JEFFREY BULL
Service/Power Release 4/24/2024 Approved JEFFREY BULL
ELECTRICAL-Final 6/5/2024 Approved JEFFREY BULL
Final 6/5/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 6/5/2024 Approved JEFFREY BULL
HVAC-Final 6/5/2024 Approved JEFFREY BULL
PLUMBING-Final 6/5/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 6/5/2024 Approved JEFFREY BULL