13541-13543 W LAZARD ST 91340
Certificate Information: 13541-13543 W LAZARD ST 91340
- Application / Permit
- 23016-20000-19518
- Plan Check / Job No.
- B23VN07830
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached garage to JADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.229. All work per WFPP.
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2023 | VICTOR CHEN |
| Corrections Issued | 6/22/2023 | VICTOR CHEN |
| Plan Check Approved | 7/13/2023 | GEORGE ALVAREZ |
| Issued | 7/14/2023 | APPLICANT |
| CofO in Progress | 4/5/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/29/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/15/2023 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 9/21/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/26/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/30/2023 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/30/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 10/30/2023 | Corrections Issued | KEVIN BERBERYAN |
| MERV13>=Rough | 10/30/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/30/2023 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 11/14/2023 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/14/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/16/2023 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 11/16/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 11/16/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/16/2023 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 11/16/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/29/2023 | Approved | ROBERT GOLD |
| Shower Pan | 11/29/2023 | Approved | ROBERT GOLD |
| Sewer | 1/29/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/28/2024 | Approved | KEVIN BERBERYAN |
| Final | 2/28/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 2/28/2024 | Approved | KEVIN BERBERYAN |
| MERV13>=Final | 2/28/2024 | Approved | KEVIN BERBERYAN |
| MERV13>=Rough | 2/28/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 2/28/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/14/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/22/2024 | OK to Issue CofO | KEVIN BERBERYAN |