6227 N NOBLE AVE 91411
Certificate Information: 6227 N NOBLE AVE 91411
- Application / Permit
- 23016-20000-19369
- Plan Check / Job No.
- B23VN07773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) 18' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- CofO Issued on 7/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | OMAR GARNICA |
| Corrections Issued | 6/19/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 10/11/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 10/18/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/22/2023 | OMAR GARNICA |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 5/28/2024 | RYAN SALAZAR |
| Permit Finaled | 7/12/2024 | RUBEN SALAS |
| CofO Issued | 7/12/2024 | RUBEN SALAS |
| Permit Finaled | 7/12/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 10/13/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Atlas Builders And Development Inc; Lic. No.: 1064138-B | , |
| Contractor | Atlas Builders; Lic. No.: 1064138-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/12/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 4/12/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 4/12/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 4/22/2024 | Approved | RYAN SALAZAR |
| Insulation | 4/22/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Wood Frame | 4/25/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 5/2/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/7/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/7/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/24/2024 | Approved | RYAN SALAZAR |
| Final | 5/24/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/24/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/24/2024 | Approved | RYAN SALAZAR |
| METHANE-Final | 5/24/2024 | Approved | RYAN SALAZAR |
| METHANE-Rough | 5/24/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/24/2024 | Approved | RYAN SALAZAR |