5754-5756 N VANTAGE AVE 91607

Certificate Information: 5754-5756 N VANTAGE AVE 91607

Application / Permit
23016-20000-19368
Plan Check / Job No.
B23VN07772
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert 310 sf portion of attached garage into a Junior Accessory Dwelling Unit & 50 sf laundry per CA Govt. Code 65852.2(e)(1)(A) and 65852.229 per
Permit Issued
Issued on 8/15/2023
Issuing Office
Current Status
CofO Issued on 12/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/21/2023 ANGELICA DAVE
Corrections Issued 6/22/2023 ANGELICA DAVE
Plan Check Approved 7/7/2023 ANGELICA MARTINEZ
No Progress 7/7/2023 ANGELICA MARTINEZ
Plan Check Approved 7/7/2023 ANGELICA MARTINEZ
Issued 8/15/2023 APPLICANT
CofO in Progress 11/8/2023 KIRK SANDERS
Permit Finaled 12/2/2023 RUBEN SALAS
CofO Issued 12/2/2023 RUBEN SALAS
Permit Finaled 12/2/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/26/2023 CARLOS AGUILERA
Sewer availability Cleared 6/26/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/27/2023 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/23/2023 Approved KIRK SANDERS
Underground Mechanical 8/23/2023 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 9/1/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 9/12/2023 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 9/12/2023 Approved CHRISTOPHER ROJAS
Underground Mechanical 9/12/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/20/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 9/20/2023 Approved KIRK SANDERS
Green Building Rough 9/20/2023 Approved KIRK SANDERS
HVAC-Rough 9/20/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 9/20/2023 Partial Approval KIRK SANDERS
Insulation 9/27/2023 Approved KIRK SANDERS
Shower Pan 9/27/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/29/2023 Approved JUAN VALENZUELA
Drywall Nailing 10/4/2023 Approved KIRK SANDERS
ELECTRICAL-Final 11/2/2023 Not Ready for Inspection KIRK SANDERS
Final 11/2/2023 Not Ready for Inspection KIRK SANDERS
Green Building Final 11/2/2023 Approved KIRK SANDERS
HVAC-Final 11/2/2023 Approved KIRK SANDERS
PLUMBING-Final 11/2/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 11/2/2023 Approved KIRK SANDERS
ELECTRICAL-Final 11/7/2023 Approved KIRK SANDERS
Final 11/7/2023 OK to Issue CofO KIRK SANDERS
PLUMBING-Final 11/7/2023 Approved KIRK SANDERS