19756 W HART ST 91306
Certificate Information: 19756 W HART ST 91306
- Application / Permit
- 23016-20000-19365
- Plan Check / Job No.
- B23VN07767
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) DETACHED 323 SF ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2023 | ALFRED RAMIREZ |
| Corrections Issued | 7/27/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/29/2023 | ALFREDO JARA |
| Plan Check Approved | 9/17/2023 | ALFREDO JARA |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 9/17/2024 | ALEXANDER HANDY |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
| CofO Issued | 9/27/2024 | JOHN JANSON |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/28/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 9/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/12/2023 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 10/12/2023 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 10/19/2023 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/20/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/6/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/6/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 12/6/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/6/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Corrections Issued | HENRY KIM |
| Insulation | 1/17/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | HENRY KIM |
| Drywall Nailing | 1/25/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/27/2024 | Approved | SCOTT SOBEL |
| Shower Pan | 8/27/2024 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/6/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 9/6/2024 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Final | 9/6/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/6/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 9/6/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/16/2024 | Approved | ALEXANDER HANDY |
| Final | 9/16/2024 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/16/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/16/2024 | Approved | ALEXANDER HANDY |