14261-14263 W DEARBORN ST 91402
Certificate Information: 14261-14263 W DEARBORN ST 91402
- Application / Permit
- 23016-20000-19331
- Plan Check / Job No.
- B23VN07754
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JADU PER GCS 65852.2(e)(1)(A) and 65852.22.
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | SERGIO MUNIZ |
| Corrections Issued | 6/17/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Plan Check Approved | 8/15/2023 | ISIS ARGUETA |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 8/2/2024 | JENNIFER RABUCHIN |
| CofO Issued | 8/19/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/30/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 9/26/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/2/2023 | Conditional Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/28/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 11/28/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/13/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 12/13/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 12/13/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 2/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 2/13/2024 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 3/4/2024 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/4/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/4/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 3/4/2024 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 3/4/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 3/7/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 3/12/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/12/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/14/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/8/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/11/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/16/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/16/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/16/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/16/2024 | Approved | JENNIFER RABUCHIN |