8136-8138 N LIMERICK AVE 91306

Certificate Information: 8136-8138 N LIMERICK AVE 91306

Application / Permit
23016-20000-19281
Plan Check / Job No.
B23VN07733
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage to new ADU per state law All work done per wfpp.
Permit Issued
Issued on 9/13/2023
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/23/2023 KHUONG TRUONG
Corrections Issued 6/25/2023 KHUONG TRUONG
Applicant returned to address corrections 8/4/2023 KHUONG TRUONG
Plan Check Approved 9/3/2023 KHUONG TRUONG
Issued 9/13/2023 APPLICANT
CofO in Progress 11/10/2025 ALEXANDER HANDY
Permit Finaled 2/23/2026 JOHN JANSON
CofO Issued 2/23/2026 JOHN JANSON
Permit Finaled 2/23/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/15/2023 CARLOS AGUILERA
Sewer availability Cleared 7/15/2023 CARLOS AGUILERA
ZA Case Cleared 7/18/2023 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 8/26/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2024 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 2/11/2025 Approved JUAN ALVARADO
Sewer 2/11/2025 Partial Approval JUAN ALVARADO
BUILDING-Rough-Frame 4/17/2025 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 4/17/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 4/17/2025 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 4/17/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 4/17/2025 Approved ALEXANDER HANDY
Sewer 4/17/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 5/19/2025 Approved ALEXANDER HANDY
Green Building Rough 5/19/2025 Approved ALEXANDER HANDY
Insulation 5/19/2025 Approved ALEXANDER HANDY
Shower Pan 5/19/2025 Approved ALEXANDER HANDY
Drywall Nailing 6/6/2025 Corrections Issued HENRY KIM
Interior/Exterior Lathing 6/6/2025 Approved HENRY KIM
Special/Order Compliance 6/6/2025 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 7/7/2025 Approved ALEXANDER HANDY
Drywall Nailing 7/7/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 11/4/2025 Approved ALEXANDER HANDY
Final 11/4/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 11/4/2025 Approved ALEXANDER HANDY
HVAC-Final 11/4/2025 Approved ALEXANDER HANDY
PLUMBING-Final 11/4/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 11/4/2025 Approved ALEXANDER HANDY