8136-8138 N LIMERICK AVE 91306
Certificate Information: 8136-8138 N LIMERICK AVE 91306
- Application / Permit
- 23016-20000-19281
- Plan Check / Job No.
- B23VN07733
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage to new ADU per state law All work done per wfpp.
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | KHUONG TRUONG |
| Corrections Issued | 6/25/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/4/2023 | KHUONG TRUONG |
| Plan Check Approved | 9/3/2023 | KHUONG TRUONG |
| Issued | 9/13/2023 | APPLICANT |
| CofO in Progress | 11/10/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
| CofO Issued | 2/23/2026 | JOHN JANSON |
| Permit Finaled | 2/23/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/15/2023 | CARLOS AGUILERA |
| ZA Case | Cleared | 7/18/2023 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2024 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 2/11/2025 | Approved | JUAN ALVARADO |
| Sewer | 2/11/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/17/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 4/17/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 4/17/2025 | Approved | ALEXANDER HANDY |
| Sewer | 4/17/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 5/19/2025 | Approved | ALEXANDER HANDY |
| Insulation | 5/19/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 5/19/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/6/2025 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 6/6/2025 | Approved | HENRY KIM |
| Special/Order Compliance | 6/6/2025 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 7/7/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| Final | 11/4/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 11/4/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 11/4/2025 | Approved | ALEXANDER HANDY |