7453 N FARMDALE AVE 91605

Certificate Information: 7453 N FARMDALE AVE 91605

Application / Permit
23016-20000-19034
Plan Check / Job No.
B23VN07603
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT (673 SQ FT) PER LAMC 12.22 A.33(c) and (d). WORK DONE PER WFPP.
Permit Issued
Issued on 7/11/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/13/2023 JEROME MAGAT PALMA
Corrections Issued 6/14/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 7/10/2023 ISIS ARGUETA
Building Plans Picked Up 7/10/2023 APPLICANT
Issued 7/11/2023 APPLICANT
CofO in Progress 1/30/2024 JOHN HAYES
Permit Finaled 4/3/2024 DANIEL ORRANTE
CofO Issued 4/3/2024 DANIEL ORRANTE
Permit Finaled 4/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/16/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/16/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/22/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/9/2023 Corrections Issued JOHN HAYES
Underground Mechanical 8/9/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/15/2023 Approved JOHN HAYES
ELECTRICAL-Rough 9/20/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/20/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 9/20/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 9/20/2023 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 9/22/2023 Approved JOHN HAYES
Interior/Exterior Lathing 10/4/2023 Approved MICHEL ABAJAN
Insulation 10/10/2023 Approved JOHN HAYES
Shower Pan 10/13/2023 Not Ready for Inspection JOHN HAYES
Drywall Nailing 10/18/2023 Approved JOHN HAYES
Shower Pan 10/18/2023 Approved JOHN HAYES
Interior/Exterior Lathing 11/6/2023 Approved CHRISTOPHER ROJAS
Pre-Inspection 11/6/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/22/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/22/2024 Corrections Issued CHRISTOPHER ROJAS
Final 1/22/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/22/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 1/22/2024 Approved JENNIFER RABUCHIN
HVAC-Final 1/22/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 1/22/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/22/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/22/2024 Approved JENNIFER RABUCHIN
Final 1/24/2024 Corrections Issued JOHN HAYES
Pre-Inspection 1/24/2024 Approved JOHN HAYES
Service/Power Release 1/24/2024 Not Ready for Inspection JOHN HAYES
Final 1/29/2024 OK to Issue CofO JOHN HAYES