700 N HILL PL # 1-28 90012

Certificate Information: 700 N HILL PL # 1-28 90012

Application / Permit
23016-20000-18990
Plan Check / Job No.
B23VN07585
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) REC ROOM AND EXERCISE ROOM TO (N) 836 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 3/6/2024
Issuing Office
Metro
Current Status
Issued on 3/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/13/2023 JESSE ARELLANO
Corrections Issued 6/13/2023 JESSE ARELLANO
Building Plans Picked Up 6/14/2023 APPLICANT
Plan Check Approved 1/17/2024 LUISANGEL VALENZUELA
Issued 3/6/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/1/2023 CELINA MORENO
Sewer availability Cleared 7/1/2023 CELINA MORENO
Historic Resource Verification Cleared 7/5/2023 MAX LODER
Eng Process Fee Ord 176,300 Cleared 7/10/2023 CELINA MORENO
Hydrant and Access approval Cleared 8/6/2023 KURT CORRAL
Tenant Habitability Plan Cleared 8/16/2023 RICARDO BOHORQUEZ
Fire Marshal Fire Life Safety Cleared 10/10/2023 WILLIAM JOHNS
DAS Clearance Cleared 1/16/2024 ALEC MOUSAKHANIAN
Hold Cleared 3/11/2024 CARMEN MERAZ

Contact Information

Contractor Buildwise Construction; Lic. No.: 1105326-B 15326 COLORADO AVE      PARAMOUNT, CA 90723

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/13/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 5/1/2024 Corrections Issued RAMAZANALI ALMASI
Wood Frame 8/20/2024 Corrections Issued LUIS CCAMACHO
Wood Frame 10/17/2024 Partial Inspection RAMAZANALI ALMASI
Wood Frame 12/6/2024 Corrections Issued RONALD JIMENEZ
Wood Frame 2/7/2025 No Access for Inspection RONALD JIMENEZ
Pre-Inspection 2/14/2025 Not Ready for Inspection ALFREDO LOPEZ
Insulation 4/24/2025 Approved RONALD JIMENEZ
Wood Frame 4/24/2025 Approved RONALD JIMENEZ
Drywall Nailing 4/25/2025 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 4/25/2025 Approved RONALD JIMENEZ
Drywall Nailing 5/6/2025 Approved RONALD JIMENEZ
Drywall Nailing 5/9/2025 Approved RONALD JIMENEZ
Final 5/28/2025 Not Ready for Inspection RONALD JIMENEZ
METHANE-Final 5/28/2025 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 5/28/2025 Not Ready for Inspection RONALD JIMENEZ
Special/Order Compliance 6/13/2025 Corrections Issued RONALD JIMENEZ
Final 7/24/2025 No Access for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 7/24/2025 No Access for Inspection RONALD JIMENEZ
Final 8/5/2025 Not Ready for Inspection RONALD JIMENEZ
Smoke Detectors 8/5/2025 Approved RONALD JIMENEZ
Final 8/8/2025 Conditional Approval RONALD JIMENEZ