1317 N AVENUE 50 90042
Certificate Information: 1317 N AVENUE 50 90042
- Application / Permit
- 23016-20000-18861
- Plan Check / Job No.
- B23VN07510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-0" X 28'-0" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/12/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/14/2023 | APPLICANT |
| Plan Check Approved | 9/26/2023 | MIROOSH KHACHATOORIAN |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 3/26/2025 | DAVID WILLIAMS |
| Permit Finaled | 3/26/2025 | DEROLD HAUFF |
| CofO Issued | 3/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/16/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 6/21/2023 | BRIAN MILLER |
| Construction near power lines | Cleared | 9/23/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/30/2023 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 1/29/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 1/29/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 2/13/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Drywall Nailing | 2/14/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/15/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/29/2024 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/22/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/28/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 6/18/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/25/2024 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 10/15/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 11/4/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/25/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/25/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/25/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 2/25/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 2/25/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/10/2025 | Approved | DAVID WILLIAMS |
| Final | 3/10/2025 | OK to Issue CofO | DAVID WILLIAMS |
| HVAC-Final | 3/10/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 3/10/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/10/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 3/10/2025 | Approved | DAVID WILLIAMS |
| Final | 3/26/2025 | OK to Issue CofO | DAVID WILLIAMS |