1317 N AVENUE 50 90042

Certificate Information: 1317 N AVENUE 50 90042

Application / Permit
23016-20000-18861
Plan Check / Job No.
B23VN07510
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-0" X 28'-0" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/26/2023
Issuing Office
Current Status
CofO Issued on 3/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2023 APPLICANT
Assigned to Plan Check Engineer 6/12/2023 ARTIN ZARUKIAN
Corrections Issued 6/12/2023 ARTIN ZARUKIAN
Building Plans Picked Up 6/14/2023 APPLICANT
Plan Check Approved 9/26/2023 MIROOSH KHACHATOORIAN
Issued 9/26/2023 APPLICANT
CofO in Progress 3/26/2025 DAVID WILLIAMS
Permit Finaled 3/26/2025 DEROLD HAUFF
CofO Issued 3/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/16/2023 TREVOR QUAN
Sewer availability Cleared 6/16/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/21/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 6/21/2023 BRIAN MILLER
Construction near power lines Cleared 9/23/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/30/2023 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 1/29/2024 Approved ROY SPAULDING
PLUMBING-Rough 1/29/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/13/2024 No Access for Inspection CRAIG VAUGHAN
Drywall Nailing 2/14/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/13/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/15/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/29/2024 Corrections Issued OSVALDO PARAMO
Interior/Exterior Lathing 5/22/2024 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/28/2024 Approved OSVALDO PARAMO
HVAC-Rough 6/18/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 9/25/2024 Approved ALIZAH MAYAGOITIA
Insulation 9/25/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Approved ROY SPAULDING
Drywall Nailing 10/15/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 11/4/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/12/2024 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 11/25/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/25/2025 Not Ready for Inspection LILIANA PORTILLO
Final 2/25/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/25/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 2/25/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 3/10/2025 Approved DAVID WILLIAMS
Final 3/10/2025 OK to Issue CofO DAVID WILLIAMS
HVAC-Final 3/10/2025 Approved DAVID WILLIAMS
PLUMBING-Final 3/10/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 3/10/2025 Approved DAVID WILLIAMS
Final 3/26/2025 OK to Issue CofO DAVID WILLIAMS