18550 W NAPA ST 91324
Certificate Information: 18550 W NAPA ST 91324
- Application / Permit
- 23016-20000-18382
- Plan Check / Job No.
- B23VN07353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 6/8/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/13/2023 | APPLICANT |
| Issued | 7/10/2023 | APPLICANT |
| CofO in Progress | 6/7/2024 | KRISTEN BEVERIDGE |
| Permit Finaled | 6/25/2024 | JOHN JANSON |
| CofO Issued | 6/25/2024 | JOHN JANSON |
| Permit Finaled | 6/25/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/10/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/10/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | CARLOS AGUILERA |
| Construction within easement | Cleared | 6/27/2023 | OSCAR CASTRO |
| Hold | Cleared | 9/15/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khansa,, Eyass; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/19/2023 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/19/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/26/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/21/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/9/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/9/2024 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/9/2024 | Approved | DAVID SCANTLIN |
| Insulation | 1/11/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 1/23/2024 | Approved | DAVID SCANTLIN |
| Shower Pan | 1/23/2024 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 1/26/2024 | Approved | DAVID SCANTLIN |
| Final | 5/6/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 5/6/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/6/2024 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/6/2024 | Approved | DAVID SCANTLIN |
| Final | 5/10/2024 | Conditional Approval | KRISTEN CAUSEY |
| Green Building Final | 5/10/2024 | Approved | KRISTEN CAUSEY |
| Final | 6/5/2024 | OK to Issue CofO | KRISTEN CAUSEY |