19422 W NORDHOFF ST 91324
Certificate Information: 19422 W NORDHOFF ST 91324
- Application / Permit
- 23016-20000-18186
- Plan Check / Job No.
- B23VN07293
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CHAGNE OF USE FROM RETAIL TO DENTAL CLINIC
- Permit Issued
- Issued on 9/9/2023
- Issuing Office
- Current Status
- Issued on 9/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2023 | PINANK PATEL |
| Corrections Issued | 6/12/2023 | PINANK PATEL |
| Applicant returned to address corrections | 7/10/2023 | JOE VO |
| Applicant returned to address corrections | 7/13/2023 | JOE VO |
| Plan Check Approved | 7/17/2023 | JOE VO |
| Issued | 9/9/2023 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 9/8/2023 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/9/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Espino Roberto; Lic. No.: 924261-B | , |
| Contractor | Marb Construction Management; Lic. No.: 924261-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/13/2023 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 11/1/2023 | Conditional Approval | DEANDRE HOFFMAN |
| T-Bar Ceiling | 12/29/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 4/26/2024 | Corrections Issued | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 4/26/2024 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 4/26/2024 | Approved | DEANDRE HOFFMAN |
| Final | 6/3/2025 | Not Ready for Inspection | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Ready | GREGORY POMISH |
| Smoke Detectors | 6/3/2025 | Not Ready for Inspection | GREGORY POMISH |
| Final | 6/20/2025 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2025 | SGSOV Not Ready | DEANDRE HOFFMAN |
| Smoke Detectors | 6/20/2025 | Approved | DEANDRE HOFFMAN |