4349-4351 W MORRO DR 91364
Certificate Information: 4349-4351 W MORRO DR 91364
- Application / Permit
- 23016-20000-18101
- Plan Check / Job No.
- B23VN07251
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN CONVERTING EXISTING 2 BEDROOMS/1 BATHROOM AT LOWER FLOOR TO ADU - 498 SF, KITCHEN REMODEL AT GROUND FLOOR WITH NON-BEARING WALL REMOVAL *NFPA-13D FIRE SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 6/12/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/12/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/17/2023 | ISIS ARGUETA |
| Issued | 8/22/2023 | APPLICANT |
| CofO in Progress | 10/11/2024 | JOHN HAYES |
| Permit Finaled | 2/13/2025 | JOHN JANSON |
| CofO Issued | 2/13/2025 | JOHN JANSON |
| Permit Finaled | 2/13/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 6/14/2023 | FERNANDO GIL |
| Specific Plan | Cleared | 7/6/2023 | JUDE HERNANDEZ |
| Specific Plan | Cleared | 7/6/2023 | JUDE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/11/2023 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 12/11/2023 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/15/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/15/2023 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 12/19/2023 | No Access for Inspection | JOHN KIDWELL |
| Drywall Nailing | 12/29/2023 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 12/29/2023 | Partial Approval | VINCENT HANLEY |
| Pre-Inspection | 4/8/2024 | Approved | MORRIS JACKSON |
| Pre-Inspection | 4/10/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/16/2024 | Corrections Issued | MORRIS JACKSON |
| Gas Test | 5/16/2024 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 5/16/2024 | Approved | MORRIS JACKSON |
| Sewer | 5/16/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 5/16/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/20/2024 | Partial Approval | JOHN HAYES |
| Insulation | 6/4/2024 | Approved | JOHN HAYES |
| Special/Order Compliance | 6/4/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 6/11/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/7/2024 | Approved | JOHN HAYES |
| Final | 8/7/2024 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/7/2024 | Approved | JOHN HAYES |
| Final | 10/11/2024 | OK to Issue CofO | JOHN HAYES |