6645-6647 N BERQUIST AVE 91307

Certificate Information: 6645-6647 N BERQUIST AVE 91307

Application / Permit
23016-20000-17895
Plan Check / Job No.
B23VN07169
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 22'-5" X 20' ATTACHED GARAGE TO (448 S.F) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 6/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2023 APPLICANT
Assigned to Plan Check Engineer 6/7/2023 ARTIN ZARUKIAN
Corrections Issued 6/7/2023 ARTIN ZARUKIAN
Building Plans Picked Up 6/12/2023 APPLICANT
Issued 6/16/2023 APPLICANT
CofO in Progress 2/27/2025 TROY SANDERS
Permit Finaled 5/28/2025 JOHN JANSON
CofO Issued 5/28/2025 JOHN JANSON
Permit Finaled 5/28/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/10/2023 CARLOS AGUILERA
Sewer availability Cleared 6/10/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/12/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/26/2024 Approved TROY SANDERS
PLUMBING-Rough 11/26/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 12/11/2024 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 12/11/2024 Approved TROY SANDERS
HVAC-Rough 12/11/2024 Approved TROY SANDERS
PLUMBING-Rough 12/11/2024 Approved TROY SANDERS
Insulation 12/16/2024 Approved TROY SANDERS
Interior/Exterior Lathing 12/16/2024 Partial Approval TROY SANDERS
Shower Pan 12/16/2024 Approved TROY SANDERS
Drywall Nailing 12/19/2024 Approved TROY SANDERS
Green Building Rough 12/19/2024 Approved TROY SANDERS
Interior/Exterior Lathing 12/19/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 2/4/2025 Approved TROY SANDERS
Final 2/4/2025 Not Ready for Inspection TROY SANDERS
Green Building Final 2/4/2025 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Not Ready TROY SANDERS
Smoke Detectors 2/4/2025 Approved TROY SANDERS
Final 2/26/2025 OK to Issue CofO TROY SANDERS
Green Building Final 2/26/2025 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved TROY SANDERS