13706-13708 W GOLETA ST 91331
Certificate Information: 13706-13708 W GOLETA ST 91331
- Application / Permit
- 23016-20000-17866
- Plan Check / Job No.
- B23VN07165
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT EXISTING ATTACHED 18'x20' GARAGE TO JADU PER 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Current Status
- Issued on 7/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/8/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/14/2023 | ADAM HEGAZI |
| Issued | 7/18/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 6/15/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/27/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 9/27/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 9/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/4/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/4/2023 | Approved | GREGG CUMMINGS |
| Sewer | 10/10/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/1/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 11/1/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 11/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/7/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/7/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 11/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/7/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/15/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/15/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2023 | Approved | GREGG CUMMINGS |
| Insulation | 11/17/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/27/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/29/2023 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 11/29/2023 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 11/29/2023 | No Access for Inspection | WILLIAM WREN |
| Shower Pan | 11/29/2023 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/12/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 12/12/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/12/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/12/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 12/12/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/18/2023 | No Access for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 12/18/2023 | No Access for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/18/2023 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/8/2024 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 1/8/2024 | No Access for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/8/2024 | No Access for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/24/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/24/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/24/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 4/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |