8701 N SUNLAND BLVD 91352

Certificate Information: 8701 N SUNLAND BLVD 91352

Application / Permit
23016-20000-17752
Plan Check / Job No.
B23VN07115
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Day Care Facility adults
Work Description
ePLAN- CHANGE OF USE FROM EXISTING OFFICE TO ADULT DAY CARE FACILITY. "COMPLY WITH DEPARTMENT ORDER effective date 10/10/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 4/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 RAPHAEL ROSAS
Corrections Issued 6/20/2023 RAPHAEL ROSAS
Quality Review Completed 6/22/2023 STEVEN KIM
Applicant returned to address corrections 12/26/2023 RAPHAEL ROSAS
Applicant returned to address corrections 1/24/2024 RAPHAEL ROSAS
Applicant returned to address corrections 3/20/2024 RAPHAEL ROSAS
Plan Check Approved 3/22/2024 RAPHAEL ROSAS
Issued 4/3/2024 APPLICANT
CofO in Progress 4/22/2025 BEHROUZ HASHEMI
Permit Finaled 4/29/2025 DAVID JAMES
CofO Issued 4/29/2025 DAVID JAMES
Permit Finaled 4/29/2025 DAVID JAMES

Permit Application Clearance Information

Comm Cor/Mini-Mall Cleared 7/1/2023 STEVEN WECHSLER
ZA Case Cleared 7/1/2023 STEVEN WECHSLER
ZA Case Cleared 7/1/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 7/5/2023 COLIN LOREDO
Sewer availability Cleared 7/5/2023 COLIN LOREDO
Comm Cor/Mini-Mall Cleared 11/21/2023 STEVEN WECHSLER
DAS Clearance Cleared 1/8/2024 Jesse Jimenez
Fire Marshal Fire Life Safety Cleared 3/15/2024 WILLIAM JOHNS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BYRON BRASHEARS, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
TIM CROWDER, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
NEVILLE REID, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
BEHROUZ HASHEMI, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
LINN MELVIN, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 6/18/2024 Corrections Issued BEHROUZ HASHEMI
Wood Frame 7/17/2024 Approved BEHROUZ HASHEMI
Wood Frame 7/17/2024 No Access for Inspection BEHROUZ HASHEMI
Insulation 7/23/2024 Partial Approval BEHROUZ HASHEMI
Drywall Nailing 7/29/2024 Not Ready for Inspection BEHROUZ HASHEMI
Drywall Nailing 7/31/2024 Approved BEHROUZ HASHEMI
Final 1/10/2025 Partial Approval BEHROUZ HASHEMI
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Not Ready BEHROUZ HASHEMI
Smoke Detectors 1/10/2025 Partial Approval BEHROUZ HASHEMI
Final 3/18/2025 Not Ready for Inspection BEHROUZ HASHEMI
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Approved BEHROUZ HASHEMI
Final 4/21/2025 OK to Issue CofO BEHROUZ HASHEMI