18749 W VICTORY BLVD 91335

Certificate Information: 18749 W VICTORY BLVD 91335

Application / Permit
23016-20000-17523
Plan Check / Job No.
B23VN07026
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE PORTION WITHIN (E) DET ADU W/ ATT GARAGE INTO A NEW REC. ROOM
Permit Issued
Issued on 6/1/2023
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2023 APPLICANT
Assigned to Plan Check Engineer 5/30/2023 LUISANGEL VALENZUELA
Corrections Issued 5/30/2023 LUISANGEL VALENZUELA
Issued 6/1/2023 APPLICANT
CofO in Progress 8/18/2023 JON MCHUGH
Permit Finaled 8/30/2023 JOHN JANSON
CofO Issued 8/30/2023 JOHN JANSON
Permit Finaled 8/30/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2023 CARLOS AGUILERA
Sewer availability Cleared 5/31/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2023 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 6/28/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 6/28/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 6/28/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 7/5/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 7/21/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 7/21/2023 Corrections Issued SEAN HAUPT
HVAC-Rough 7/21/2023 Corrections Issued SEAN HAUPT
PLUMBING-Rough 7/21/2023 Approved SEAN HAUPT
Pre-Inspection 7/25/2023 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 7/25/2023 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Approved JEFFREY PARD
Insulation 7/27/2023 Approved JEFFREY PARD
Drywall Nailing 8/2/2023 Approved JON MCHUGH
Interior/Exterior Lathing 8/2/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 8/15/2023 Approved JON MCHUGH
ELECTRICAL-Final 8/15/2023 Corrections Issued JON MCHUGH
Final 8/15/2023 Not Ready for Inspection JON MCHUGH
HVAC-Final 8/15/2023 Approved JON MCHUGH
PLUMBING-Final 8/15/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 8/15/2023 Approved JON MCHUGH
ELECTRICAL-Final 8/18/2023 Approved JON MCHUGH
Final 8/18/2023 Partial Approval JON MCHUGH
PLUMBING-Final 8/18/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved JON MCHUGH
Final 8/21/2023 OK to Issue CofO JON MCHUGH