6736 W FOOTHILL BLVD 91042
Certificate Information: 6736 W FOOTHILL BLVD 91042
- Application / Permit
- 23016-20000-17083
- Plan Check / Job No.
- B23VN06840
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Drive Through Fast Food
- Work Description
- TENANT IMPROVEMENT FOR (E) DRIVE-THRU COFFEE SHOP - core/shell building under permit 23010-20000-01092.
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 7/19/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/19/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 9/5/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 6/10/2024 | SERGIO GUTIERREZ |
| Issued | 6/24/2024 | APPLICANT |
| Permit Finaled | 4/8/2025 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/7/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 8/7/2023 | YINGSHI HUANG |
| DAS Clearance | Cleared | 8/11/2023 | Rodolfo Arias |
| Green Code | Cleared | 9/26/2023 | MICHAEL AYERS |
| Specific Plan | Cleared | 2/8/2024 | YINGSHI HUANG |
| ZA Case | Cleared | 2/8/2024 | YINGSHI HUANG |
| Food Service Establishment | Cleared | 3/22/2024 | RAMESHBHAIR PATEL |
| Food establishment approval | Cleared | 4/22/2024 | LACDHS APPROVED |
Contact Information
| Architect | Winkler,, Page; Lic. No.: C31839 | 14558 LUNA MEDIA SAN DIEGO, CA 92127 |
| Architect | Winkler,, Page; Lic. No.: NA31839 | , |
| Contractor | Cirks Construction Inc; Lic. No.: 763589-B | , |
| Contractor | K D C Construction; Lic. No.: 763589-B | , |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/27/2024 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 12/31/2024 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 1/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 1/6/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 1/7/2025 | Partial Approval | JOHN KITCKO |
| Light Gage Steel Frame | 1/7/2025 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 1/8/2025 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 1/9/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 1/27/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 1/28/2025 | Partial Approval | GREGORY POMISH |
| Final | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Final | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 4/8/2025 | Permit Finaled | DANNY RODRIGUEZ |
| Green Building Final | 4/8/2025 | Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 4/8/2025 | Approved | DANNY RODRIGUEZ |