5038 N IRVINE AVE 91601

Certificate Information: 5038 N IRVINE AVE 91601

Application / Permit
23016-20000-16966
Plan Check / Job No.
B23VN06777
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'2" X 24'2" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER.
Permit Issued
Issued on 12/11/2023
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 MADISON ODELL
Corrections Issued 6/1/2023 MADISON ODELL
Applicant returned to address corrections 8/24/2023 ALEC MOUSAKHANIAN
Plan Check Approved 8/29/2023 ALEC MOUSAKHANIAN
Issued 12/11/2023 APPLICANT
CofO in Progress 3/26/2025 JAVIER RAMOS JR
Permit Finaled 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/12/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/12/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/14/2023 DAGOVERTO GUERRERO
Specific Plan Cleared 8/7/2023 JOANNA MARROQUIN
Specific Plan Cleared 8/7/2023 JOANNA MARROQUIN

Contact Information

Contractor Bellagio Design Build Corporation; Lic. No.: 935571-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/12/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 1/23/2024 Corrections Issued CRAIG DAVIS
Footing/Foundation/Slab 1/23/2024 Partial Approval CRAIG DAVIS
PLUMBING-Rough 1/23/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 1/23/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 1/25/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 1/25/2024 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 1/25/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/7/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 3/7/2024 Approved KIRK SANDERS
PLUMBING-Rough 3/7/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 3/19/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/19/2024 Corrections Issued KIRK SANDERS
MERV13>=Rough 3/19/2024 Approved KIRK SANDERS
Sewer 3/19/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/29/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/29/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 3/29/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/3/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 4/3/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/3/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 4/3/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 4/3/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/5/2024 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 4/5/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 4/5/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/5/2024 Partial Inspection CHRISTOPHER ROJAS
Underground Mechanical 4/5/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/10/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/10/2024 Approved MISAEL ESPARZA
Shower Pan 4/10/2024 Approved MISAEL ESPARZA
Pre-Inspection 5/9/2024 Partial Approval CHRISTOPHER ROJAS
Final 6/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Final 6/21/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 6/21/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 6/21/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 6/21/2024 Approved CHRISTOPHER ROJAS
Final 2/18/2025 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Final 2/24/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/24/2025 SGSOV Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/25/2025 Approved JAVIER RAMOS JR
Final 3/25/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/25/2025 Approved JAVIER RAMOS JR
HVAC-Final 3/25/2025 Approved JAVIER RAMOS JR