12606 W TIARA ST 91607

Certificate Information: 12606 W TIARA ST 91607

Application / Permit
23016-20000-16900
Plan Check / Job No.
B23VN06761
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'6" X 20'4" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). WORK TO BE DONE PER WFPP DESIGN.
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
CofO Issued on 4/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/26/2023 SERGIO MUNIZ
Corrections Issued 5/27/2023 SERGIO MUNIZ
Building Plans Picked Up 5/30/2023 APPLICANT
Issued 9/6/2023 APPLICANT
CofO in Progress 4/8/2024 JUAN VALENZUELA
Permit Finaled 4/19/2024 RUBEN SALAS
CofO Issued 4/19/2024 RUBEN SALAS
Permit Finaled 4/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/31/2023 CARLOS AGUILERA
Sewer availability Cleared 5/31/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/1/2023 CARLOS AGUILERA
Construction near power lines Cleared 9/6/2023 TINA MIRANDA

Contact Information

Contractor Neo Builders Inc; Lic. No.: 1061134-B 6238 ALCOVE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/7/2023 Approved KIRK SANDERS
Underground Mechanical 11/7/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 11/29/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 11/29/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval KIRK SANDERS
Green Building Rough 11/29/2023 Approved KIRK SANDERS
HVAC-Rough 11/29/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 11/29/2023 Approved KIRK SANDERS
Underground Mechanical 11/29/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 12/5/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/7/2023 Partial Approval KIRK SANDERS
HVAC-Rough 12/7/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 12/7/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 12/12/2023 Approved JUAN VALENZUELA
Insulation 12/12/2023 Approved JUAN VALENZUELA
Drywall Nailing 12/18/2023 Approved MISAEL ESPARZA
Shower Pan 12/18/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/20/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/8/2024 Corrections Issued JOSE AVILA
HVAC-Final 3/8/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 3/8/2024 Approved JOSE AVILA
ELECTRICAL-Final 3/20/2024 Not Ready for Inspection JOSE AVILA
Final 3/20/2024 Not Ready for Inspection JOSE AVILA
Green Building Final 3/20/2024 Approved JOSE AVILA
HVAC-Final 3/20/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 3/20/2024 Approved JOSE AVILA
ELECTRICAL-Final 4/2/2024 Approved JOSE AVILA
Final 4/2/2024 Corrections Issued JOSE AVILA
Final 4/4/2024 OK to Issue CofO JUAN VALENZUELA