15634-15636 W TUBA ST 91343

Certificate Information: 15634-15636 W TUBA ST 91343

Application / Permit
23016-20000-16688
Plan Check / Job No.
B23VN06676
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert (E) Garage to (N) 364 sf JADU per GCS 65852.2(e)(1)(A) and 65852.22. All work per WFPP
Permit Issued
Issued on 10/2/2023
Issuing Office
Current Status
Issued on 10/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 5/26/2023 AMY GUEVARRA
Corrections Issued 5/27/2023 AMY GUEVARRA
Applicant returned to address corrections 8/9/2023 AMY GUEVARRA
Applicant returned to address corrections 9/7/2023 AMY GUEVARRA
Plan Check Approved 9/16/2023 EDWIN ESPIN
Issued 10/2/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/13/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/13/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/13/2023 TAL SHEMEN
Sewer availability Cleared 6/13/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/19/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 10/20/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/20/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/20/2023 Partial Approval JAVIER RAMOS JR
Sewer 10/20/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/31/2024 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 1/31/2024 Approved ROBERT GOLD
Green Building Rough 1/31/2024 Approved ROBERT GOLD
HVAC-Rough 1/31/2024 Corrections Issued ROBERT GOLD
PLUMBING-Rough 1/31/2024 Corrections Issued ROBERT GOLD
Shower Pan 1/31/2024 Approved ROBERT GOLD
BUILDING-Rough-Frame 2/28/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 2/28/2024 Approved JAVIER RAMOS JR
MERV13>=Rough 2/28/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/28/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/3/2024 Approved JAVIER RAMOS JR
Insulation 4/3/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/3/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/3/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 4/3/2024 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 4/29/2024 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/23/2024 Approved JAVIER RAMOS JR