9939-9941 N BABBITT AVE 91325
Certificate Information: 9939-9941 N BABBITT AVE 91325
- Application / Permit
- 23016-20000-16492
- Plan Check / Job No.
- B23VN06622
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT 26'-3" x 19'-9" (E) ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER WFPP.
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/23/2023 | GIOVANNY CHAVEZ |
| Building Plans Picked Up | 5/24/2023 | APPLICANT |
| Applicant returned to address corrections | 7/26/2023 | ROSENDO MEDINA |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | ROBERT GOLD |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 5/31/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | NIKKI ZULUETA |
| Grading Pre-Inspection | Cleared | 7/26/2023 | MICHAEL TEMPLE |
| Hold | Cleared | 9/15/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/28/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/28/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/18/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/18/2023 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 10/18/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 10/27/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 11/1/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 11/1/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/1/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 11/1/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 11/1/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/8/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/8/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/28/2024 | Approved | JAVIER RAMOS JR |
| Final | 8/28/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/28/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 8/28/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/28/2024 | Approved | JAVIER RAMOS JR |
| Final | 10/18/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 10/18/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/1/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/1/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 11/1/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/1/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/11/2024 | OK to Issue CofO | JAVIER RAMOS JR |