9939-9941 N BABBITT AVE 91325

Certificate Information: 9939-9941 N BABBITT AVE 91325

Application / Permit
23016-20000-16492
Plan Check / Job No.
B23VN06622
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT 26'-3" x 19'-9" (E) ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER WFPP.
Permit Issued
Issued on 7/28/2023
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 5/23/2023 GIOVANNY CHAVEZ
Corrections Issued 5/23/2023 GIOVANNY CHAVEZ
Building Plans Picked Up 5/24/2023 APPLICANT
Applicant returned to address corrections 7/26/2023 ROSENDO MEDINA
Issued 7/28/2023 APPLICANT
CofO in Progress 12/12/2024 ROBERT GOLD
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/31/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 5/31/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/1/2023 NIKKI ZULUETA
Grading Pre-Inspection Cleared 7/26/2023 MICHAEL TEMPLE
Hold Cleared 9/15/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/28/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/28/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 10/18/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/18/2023 Partial Approval JAVIER RAMOS JR
Wood Frame 10/18/2023 Partial Approval JAVIER RAMOS JR
Insulation 10/27/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 11/1/2023 Approved JAVIER RAMOS JR
Insulation 11/1/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/1/2023 Partial Approval JAVIER RAMOS JR
Shower Pan 11/1/2023 Approved JAVIER RAMOS JR
Wood Frame 11/1/2023 Approved JAVIER RAMOS JR
Drywall Nailing 1/8/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/8/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/28/2024 Approved JAVIER RAMOS JR
Final 8/28/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/28/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 8/28/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/28/2024 Approved JAVIER RAMOS JR
Final 10/18/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 10/18/2024 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 11/1/2024 Approved JAVIER RAMOS JR
Final 11/1/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 11/1/2024 Approved JAVIER RAMOS JR
HVAC-Final 11/1/2024 Approved JAVIER RAMOS JR
Final 12/11/2024 OK to Issue CofO JAVIER RAMOS JR