8740 N MATILIJA AVE 91402
Certificate Information: 8740 N MATILIJA AVE 91402
- Application / Permit
- 23016-20000-15285
- Plan Check / Job No.
- B23VN06128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert (E) recreation room/garage and carport to (N) ADU per GCS 65852.2(e)(1)(A) and engr calcs
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Current Status
- CofO Issued on 6/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2023 | AMY GUEVARRA |
| Corrections Issued | 5/26/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 6/15/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/7/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/11/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/13/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/21/2024 | ARSALAN SHABESTARI |
| Issued | 4/15/2024 | APPLICANT |
| CofO in Progress | 5/19/2025 | VINCENT HANLEY |
| No Progress | 5/19/2025 | VINCENT HANLEY |
| CofO in Progress | 5/19/2025 | VINCENT HANLEY |
| CofO in Progress | 5/19/2025 | VINCENT HANLEY |
| CofO in Progress | 5/22/2025 | VINCENT HANLEY |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
| CofO Issued | 6/24/2025 | RUBEN SALAS |
| Permit Finaled | 6/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | FERNANDO GIL |
| Roof/Waste drainage to street | Cleared | 5/31/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 5/31/2023 | FERNANDO GIL |
| Construction within easement | Cleared | 8/22/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/24/2024 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/25/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/25/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 11/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 11/13/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/3/2025 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 3/20/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/26/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/16/2025 | Approved | VINCENT HANLEY |
| Final | 5/16/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 5/16/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/16/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/16/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/16/2025 | Approved | VINCENT HANLEY |
| Final | 5/22/2025 | OK to Issue CofO | VINCENT HANLEY |