12257 W MIRANDA ST 91607

Certificate Information: 12257 W MIRANDA ST 91607

Application / Permit
23016-20000-15117
Plan Check / Job No.
B23VN06071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage 20' x 20' into an ADU NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT (SEE COMMENTS)
Permit Issued
Issued on 6/13/2023
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/16/2023 RAHEL BEYENE
Corrections Issued 5/17/2023 RAHEL BEYENE
Plan Check Approved 6/12/2023 JOE VO
Issued 6/13/2023 APPLICANT
CofO in Progress 7/27/2024 OGANES TARAKHCHYAN
Permit Finaled 8/14/2024 DANIEL ORRANTE
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/8/2023 FERNANDO GIL
Sewer availability Cleared 6/8/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 6/9/2023 FERNANDO GIL

Contact Information

Contractor Heskel Developments; Lic. No.: 1081833-B       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/1/2023 Approved KIRK SANDERS
Underground Mechanical 8/1/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 12/13/2023 Approved JOSE AVILA
HVAC-Rough 12/13/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/13/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 12/21/2023 Approved KIRK SANDERS
HVAC-Rough 12/27/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 2/26/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 2/26/2024 Approved JOSE AVILA
Green Building Rough 3/6/2024 Approved JOSE AVILA
Insulation 3/6/2024 Approved JOSE AVILA
Drywall Nailing 3/12/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 3/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/22/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 3/22/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 6/18/2024 Approved VINCENT HANLEY
HVAC-Final 6/27/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 6/27/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/26/2024 Approved OGANES TARAKHCHYAN
Final 7/26/2024 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 7/26/2024 Approved OGANES TARAKHCHYAN