7719 N CASE AVE 91352
Certificate Information: 7719 N CASE AVE 91352
- Application / Permit
- 23016-20000-14902
- Plan Check / Job No.
- B23VN05968
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DET 18'4"X46'2" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).- PER WFPP AND ENGINEER DETAILS
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 5/11/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/12/2023 | APPLICANT |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 10/12/2023 | JENNIFER RABUCHIN |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | DAGOVERTO GUERRERO |
| ZI | Cleared | 6/10/2023 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 6/12/2023 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | MATTHEW NELSON |
| Sewer | 6/27/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 6/27/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 7/3/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/3/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 7/5/2023 | Approved | MATTHEW NELSON |
| Insulation | 7/10/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/12/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/12/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/17/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 7/17/2023 | Approved | MATTHEW NELSON |
| Final | 8/11/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/11/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 8/11/2023 | Approved | MATTHEW NELSON |
| Final | 8/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/28/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/31/2023 | Not Required | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/12/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/12/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 10/12/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/12/2023 | Approved | JENNIFER RABUCHIN |