7719 N CASE AVE 91352

Certificate Information: 7719 N CASE AVE 91352

Application / Permit
23016-20000-14902
Plan Check / Job No.
B23VN05968
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DET 18'4"X46'2" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).- PER WFPP AND ENGINEER DETAILS
Permit Issued
Issued on 6/13/2023
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 HAYATO TSUCHIYA
Corrections Issued 5/11/2023 HAYATO TSUCHIYA
Building Plans Picked Up 5/12/2023 APPLICANT
Issued 6/13/2023 APPLICANT
CofO in Progress 10/12/2023 JENNIFER RABUCHIN
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/18/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 5/18/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/19/2023 DAGOVERTO GUERRERO
ZI Cleared 6/10/2023 STEVEN WECHSLER
Construction near power lines Cleared 6/12/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2023 Approved MATTHEW NELSON
PLUMBING-Rough 6/22/2023 Partial Approval MATTHEW NELSON
Sewer 6/27/2023 Approved WILLIAM WREN
Underground Mechanical 6/27/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 7/3/2023 Approved MATTHEW NELSON
PLUMBING-Rough 7/3/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 7/5/2023 Approved MATTHEW NELSON
Insulation 7/10/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 7/12/2023 Approved MATTHEW NELSON
Green Building Rough 7/12/2023 Approved MATTHEW NELSON
Drywall Nailing 7/17/2023 Approved MATTHEW NELSON
Shower Pan 7/17/2023 Approved MATTHEW NELSON
Final 8/11/2023 Corrections Issued MATTHEW NELSON
Green Building Final 8/11/2023 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 8/11/2023 Approved MATTHEW NELSON
Final 8/28/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/28/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Not Ready JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 8/31/2023 Not Required JENNIFER RABUCHIN
ELECTRICAL-Final 10/12/2023 Approved JENNIFER RABUCHIN
Final 10/12/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/12/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/12/2023 Approved JENNIFER RABUCHIN