11620 W ADDISON ST 91601

Certificate Information: 11620 W ADDISON ST 91601

Application / Permit
23016-20000-14887
Plan Check / Job No.
B23VN05961
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/31/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 RAMA DABADGE
Corrections Issued 5/15/2023 RAMA DABADGE
Building Plans Picked Up 5/22/2023 APPLICANT
Applicant returned to address corrections 12/20/2023 ALFRED RAMIREZ
Plan Check Approved 1/29/2024 MOHAMMAD ESMAILI
Issued 1/31/2024 APPLICANT
CofO in Progress 1/15/2025 CHRISTOPHER ROJAS
Permit Finaled 1/28/2025 RUBEN SALAS
CofO Issued 1/28/2025 RUBEN SALAS
Permit Finaled 1/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/16/2023 NIKKI ZULUETA
Sewer availability Cleared 5/16/2023 NIKKI ZULUETA
Miscellaneous Cleared 5/18/2023 BRENNEN OBETO
Specific Plan Cleared 5/22/2023 JOANNA MARROQUIN
ZI Cleared 5/22/2023 JOANNA MARROQUIN
ZI Cleared 5/22/2023 JOANNA MARROQUIN
Eng Process Fee Ord 176,300 Cleared 5/25/2023 NIKKI ZULUETA
Construction near power lines Cleared 8/14/2023 RIDWAN HARDY

Contact Information

Contractor Romano Builders Inc; Lic. No.: 922936-B 14407 GILMORE STREET #101      VAN NUYS, CA 91401
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/27/2024 Corrections Issued KIRK SANDERS
Sewer 2/27/2024 Approved KIRK SANDERS
Underground Mechanical 2/27/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 3/1/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 3/6/2024 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 3/12/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/5/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 4/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/16/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/16/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 4/16/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/16/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/16/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 5/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/20/2024 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 5/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/4/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/24/2024 Partial Approval ROBERT GOLD
Insulation 7/8/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/9/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 7/9/2024 Approved CHRISTOPHER ROJAS
Insulation 7/9/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/11/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 7/22/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 7/25/2024 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 7/29/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 12/2/2024 Partial Inspection CHRISTOPHER ROJAS
Final 12/2/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 12/2/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 12/2/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 12/2/2024 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 12/2/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 12/20/2024 Approved CHRISTOPHER ROJAS
Final 12/20/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 12/20/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Final 12/20/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Final 12/20/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 12/27/2024 Partial Approval CHRISTOPHER ROJAS
Final 12/27/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 12/27/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Final 12/27/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Final 12/27/2024 Approved CHRISTOPHER ROJAS
Final 1/15/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 1/15/2025 Approved CHRISTOPHER ROJAS