18510 W ASUNCION ST 91326

Certificate Information: 18510 W ASUNCION ST 91326

Application / Permit
23016-20000-14758
Plan Check / Job No.
B23VN05909
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN convert 480 ft Detached garage into an Accessory Dwelling Unit (ADU). GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/19/2023
Issuing Office
Current Status
CofO Issued on 11/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/10/2023 DANIEL SANJUAN
Corrections Issued 5/11/2023 DANIEL SANJUAN
Plan Check Approved 5/19/2023 DANIEL SANJUAN
Issued 5/19/2023 APPLICANT
CofO in Progress 11/21/2023 STEVEN BACK
Permit Finaled 11/22/2023 JOHN JANSON
CofO Issued 11/22/2023 JOHN JANSON
Permit Finaled 11/22/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/12/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/12/2023 LEE GUILBEAUX
Sewer availability Cleared 5/12/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/15/2023 LEE GUILBEAUX

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor C I D Builders And Developers Inc; Lic. No.: 958193-B       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2023 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 6/13/2023 Approved JEFFREY PARD
Footing/Foundation/Slab 6/13/2023 Approved STEVEN BACK
ELECTRICAL-Rough 7/24/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Corrections Issued JEFFREY BULL
HVAC-Rough 7/24/2023 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 7/24/2023 Approved JEFFREY BULL
HVAC-Rough 8/16/2023 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 9/7/2023 Partial Approval STEVEN BACK
Shower Pan 9/7/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 9/12/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Approved STEVEN BACK
HVAC-Rough 9/12/2023 Approved STEVEN BACK
MERV13>=Rough 9/12/2023 Approved STEVEN BACK
Insulation 9/19/2023 Approved HENRY KIM
Interior/Exterior Lathing 9/19/2023 Approved HENRY KIM
Drywall Nailing 9/27/2023 Approved STEVEN BACK
Final 11/7/2023 Corrections Issued HORACE FULTZ
MERV13>=Final 11/7/2023 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/7/2023 SGSOV Approved HORACE FULTZ
Smoke Detectors 11/7/2023 Approved HORACE FULTZ
Final 11/13/2023 Corrections Issued STEVEN BACK
Final 11/20/2023 OK to Issue CofO STEVEN BACK